Summary report of supervision construction work
Work summary, year-end summary, half-year summary and quarterly summary are the most common and universal. Next, I'll show you five model essays on the summary report of supervision construction work, hoping to help you!

Summary report of supervision construction 1

I. Overview of the Project

Liupanshui Vocational and Technical College 1# Complex Building is a six-story frame structure with a total construction area of 27,500 square meters. Reinforced concrete manual digging pile foundation is adopted, and the main body is cast-in-place reinforced concrete frame structure; Cast-in-place reinforced concrete beamless floor technology, the second to sixth floors of the outer wall are made of real stone paint, the first floor is made of azure square brick, and the inner wall is made of porcelain powder; The ground is terrazzo, and the academic lecture hall and hall are granite plates; The window is a white plastic steel window with sky blue glass; The roof adopts rigid and flexible waterproof layer, and the insulation layer is cement expanded perlite.

Second, the supervision organization and supervision personnel

After the two sides signed the Construction Supervision Entrustment Contract, the overall objectives of project quality, progress and investment supervision were determined. Establish the project establishment organization, namely Liupanshui Vocational and Technical College 1# Comprehensive Building Project Supervision Department. Determine Tan Re as the chief supervision engineer of the project, Li as the general manager of the company, and Zhang Rong Qi Yukui as the on-site professional supervision engineer. According to the supervision contract and the Code for Supervision of Construction Projects, the supervision objectives are decomposed, and the responsibilities of the chief supervision engineer and professional supervision engineer are defined. Make the supervision work institutionalized, standardized and standardized.

Third, the performance of the supervision contract

Since the signing of the supervision entrustment contract, our company has attached great importance to this project and established the project supervision department of Liupanshui Vocational and Technical College 1# Complex Building in time. The supervision plan, supervision implementation rules, engineering construction supervision work system, construction management supervision regulations, supervision work three control plans and supervision work procedures are compiled. According to the relevant national and local regulations and supervision contracts, decompose the supervision objectives. Clarify the responsibilities of the chief supervision engineer, professional supervision engineer and supervisor, and institutionalize, standardize and standardize the supervision work in strict accordance with the company ISO 9001-20 _ _ _. According to the project quality, progress, investment control objectives and other construction contract objectives required by the owner, collect all kinds of information in the process of project construction in time, and provide detailed supervision monthly report to the owner every month to make the owner know the project progress from beginning to end. The control target of project supervision has reached the contract requirements, and the project supervision department has fully fulfilled the obligations and responsibilities entrusted by the supervision contract and successfully completed the supervision task in the project construction stage.

Fourth, means of supervision.

Quality control: Engineering quality control is an important part of supervision work. We carry out supervision and management in strict accordance with the construction drawings, construction and acceptance specifications, quality inspection and evaluation standards of construction and installation projects and the quality objectives agreed in this project contract. In the quality control of the whole construction process of this project, combined with the actual situation of this project, it is divided into three processes: pre-control, in-process inspection and post-acceptance, among which pre-control is the main one. In the actual operation process, strictly check the contractor's quality assurance and management system. Check the certificates of managers and special operators at all levels, and verify the measurement, positioning and setting-out of the construction unit.

Carefully examine the contractor's construction organization design and put forward many rationalization suggestions. A strict inspection system has been implemented for materials, equipment and components. For building materials, equipment and components entering the construction site, there should be corresponding certificates, test reports and use licenses. Must be issued. After important materials, equipment and components enter the site, site supervisors will witness sampling and inspection, and strictly implement the witness sampling system. Require the construction unit to fill in the material/component/equipment inspection form and submit it to the supervision department for review. Non-conforming and unqualified products are definitely not allowed to be used in engineering, and quality hidden dangers are eliminated by controlling raw materials in advance. For important and key sub-divisional projects, the construction unit is strongly required to put forward relevant construction plans, compile construction technology, raw material use, labor allocation and quality assurance measures into special construction plans, submit them to the supervision department for review, and carry out cumulative examination and approval on the special plans of construction organization design. After the audit, the construction unit is required to strictly implement the plan to avoid blind construction. Before concrete and mortar construction, the mixture ratio must be issued and inspected, and the concrete pouring application form must be filled in before concrete construction.

In the process of construction, we carry out patrol inspection, on-site supervision and parallel inspection. 24-hour on-site supervision should be implemented for concrete construction sub-projects. Once the problem is found, the contractor shall be informed orally to correct it, and then the supervision engineer will issue a supervision notice to inform the contractor and supervise the implementation. Require the construction unit to conduct self-inspection for each sub-item or sub-item project. After passing the self-inspection, fill in the project quality inspection form, attach the inspection quality inspection evaluation form of the inspection lot, and submit it to the supervision department for signature. After detailed verification according to the reported project and site, the construction of next working procedure can be carried out. During the construction process, the acceptance system shall be implemented, focusing on checking the positioning and setting-out, foundation trench acceptance, foundation reinforcement, main structure steel binding, roof waterproofing, pipeline pressure test, insulation resistance test, power system debugging and other related important links. All these should be accepted by the relevant units. After the above effective measures and strict standardized management, the acceptance of the basic division and the main division has reached the qualified standard. Supervise and urge the contractor to keep the quality assurance data synchronized with the project progress and improve the project data in time. When the project meets the conditions for submission, timely coordinate and organize the construction unit, construction contractor and supervisor to participate in the pre-acceptance, conduct a comprehensive inspection of the project quality and use function, and timely sort out the minutes of the pre-acceptance meeting.

Schedule control: From the beginning of the project, we urge the contractor to prepare the general construction schedule, construction schedule network diagram and monthly schedule according to the construction contract. In the process of construction, reasonable suggestions were put forward to the contractor, which accelerated the progress of the project while ensuring the quality of the project. Make a regular meeting system, hold a regular meeting of on-site engineering every Monday, coordinate and solve the problems existing in construction in time, and supervise the implementation of the plan; When it is found that the project seriously deviates from the plan, we will promptly organize the contractor to analyze the reasons, study measures and correct the deviation in time; Strictly urge the contractor's personnel, materials and construction machinery to arrive in time, which provides a strong guarantee for achieving the goals agreed in the contract.

Investment control: We strictly implement the payment procedures in the construction contract, carefully examine the contractor's monthly completion report and monthly payment report, and issue payment vouchers according to the amount approved by the owner. Strictly review and control the engineering change, technical approval form and on-site economic visa to ensure the investment plan objectives of the owner.

Verb (abbreviation of verb) supervises the effectiveness of work.

1. Project progress: The main structure of the artificial tunnel project is basically in line with the progress. In the later stage of decoration and installation, due to objective factors such as decoration scheme selection, design selection and corridor increase, the total progress is delayed and the construction period is delayed by about 7 months. At present, except the exterior wall real stone paint, the quantities in the contract and design documents have been completed and pre-accepted, reaching the completion acceptance conditions.

2. Project investment: Through strict examination of project changes, on-site visa, monthly completion of engineering quantity and other measures, the investment control of this project basically reaches the planned pre-control goal and conforms to the investment plan determined by the owner.

3. Project quality: All inspection lots and subdivisional works can be carefully organized during the construction process, and there are no major quality accidents and quality and safety hazards. The construction quality meets the requirements of the construction quality acceptance specification.

4. Contract performance: This project has completed the engineering quantity in the design documents according to the requirements of design and construction acceptance specifications. Project completion data and other related files are written neatly and the content is basically complete. The project of this unit basically meets the requirements of completion acceptance, and the supervisor agrees to the completion acceptance.

Whether the above evaluation opinions are appropriate or insufficient, please give your valuable opinions to the leaders and experts attending the meeting. Thank you!

Summary report of supervision construction II

I. Overview of the Project

The project is located in Long Fu Industrial Park, jiaomei Development Zone. The road and drainage works of Long Fu Industrial Park 13#(N28-N29) start from the tangent point of bell mouth 32 meters east of N28 to 4.5 meters east of N29. The length of the route is 263.5m, and the cross-sectional width of the road is19m, in which: the motorway is 2× 4.5m and the sidewalk is 2× 5m. The expressway adopts cement stabilized subgrade and cement concrete rigid pavement, the sidewalk is backfilled with soil after kerbs are set, and rainwater, sewage pipes, rainwater and sewage cross pipes and other units are buried in the road. The project quality is supervised by Longhai Construction Engineering Quality Supervision Station.

This project started on _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Second, the name of the unit and the project leader.

Construction unit: Fujian Longhai Economic Development Co., Ltd.

Project leader:

Designer: Xiamen Shenzhong Architectural Design Institute

Project leader:

Supervision unit: Zhangzhou Zheng Guang Engineering Construction Supervision Co., Ltd.

Chief Supervision Engineer: He Huilong

Construction unit: Fujian Dongxing Construction Engineering Co., Ltd.

Project manager:

Quality supervision unit: Longhai Construction Engineering Quality Supervision Station

Project leader: Zeng Baoxiang

Three. Contents and methods of supervision work

1. Supervise and inspect the quality assurance system established by the contractor.

2. Check the on-site positioning axis and elevation piles, and review the retest results submitted by the contractor.

3. Review the quality, specifications and quality of raw materials, semi-finished products, finished products and equipment that the contractor intends to use in this project, and witness sampling as required, 100% witness inspection. It can only be used after re-inspection.

4. Supervise the contractor to carry out the construction in strict accordance with the construction contract, current specifications, procedures, standards, design documents and construction procedures, and comprehensively control the project quality by means of standing by, patrolling, testing, testing and acceptance.

5. Check and control the quality progress of each process, conduct re-inspection and visa for concealed works, and urge the construction unit to sort out the construction technical files.

6. Supervisors shall be stationed at the site, and timely issue supervision notices to the places with quality problems, requiring rectification, and at the same time, accept irregular inspections by the supervisors of the municipal quality supervision station to ensure the engineering quality.

Fourth, the project quality control situation

1, in the engineering quality control work, implement the guiding ideology of giving priority to pre-control, supplemented by rectification, all-round and whole-process monitoring, pay attention to effective control of each construction link, and strictly control the quality of each working procedure.

2. The chief supervision engineer shall organize the supervisors of the project department to be familiar with the construction drawings, and put forward opinions and suggestions on the problems existing in the drawings to the design unit through the construction unit; Supervise in strict accordance with the design drawings.

3. Strictly implement the examination and approval system for concrete pouring. Before concrete pouring, the construction team leaders of reinforcement, formwork and water and electricity shall pass the self-inspection. After the quality inspector has passed the inspection, the concrete can be poured only after being signed by the professional supervision engineer.

4, according to the specific situation of the project, hold regular site meetings, presided over by the chief supervision engineer, and attended by contractors, project managers, technical directors and quality directors of various professional departments, focusing on solving the quality problems existing in the construction at this stage, coordinating the cooperation problems existing in the construction process by the owner, design and construction units, and putting forward the quality requirements for the next stage.

5, in the engineering construction, strictly implement the current national construction quality acceptance standards and relevant quality acceptance standards, mandatory provisions of engineering construction; Strengthen quality tracking and monitoring, and strictly control the quality of construction process mainly through on-site observation, on-site inspection, measurement and test.

6, the owner's representative to the site inspection from time to time, points out the quality problems in the construction process, and urges the construction unit supervision personnel to carry out rectification; Some materials and brands designated by the Owner have been inspected by the Owner during site construction.

7. Longhai city construction engineering quality supervision station related professional supervisors to intermediate acceptance of the main branch project:

(1) teaching building-20 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.

Foundation and foundation acceptance, the main structure acceptance in _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _;

(2) Library-20 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Foundation and foundation acceptance, the main structure acceptance in _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _;

(3) Acceptance of pile foundation in dormitory building-20 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.

Foundation and foundation acceptance, the main structure acceptance in _ _ _ _ _ _ _ _ _ _ _ _.

(4) The above acceptance has reached the qualified grade standard.

8. The supervision engineer shall organize supervisors of various disciplines to conduct preliminary acceptance of the completed project in _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _. Check the indoor data of the construction unit, and the data are basically complete. The construction unit has completed the contents agreed in the contract and the acceptance conditions required by the owner. The supervision unit issued the quality evaluation report of the teaching building and library on June 20, and the quality evaluation report of the dormitory building on June 20, and agreed that the construction unit should declare the pre-acceptance.

9. The supervisor of Zhangzhou Quality Supervision Station made a pre-acceptance of the project and put forward the following main problems:

(1) Improper waterproof treatment of expansion joints leads to water seepage;

(2) The width of evacuation stairs is not enough, and the height of stair handrails is not enough;

(3) The sealant of plastic-steel window leaks, and no anti-collision pad is set;

(4) There are no handrails on both sides of the barrier-free passage;

(5) There is no frame joint on the roof parapet.

10, The construction unit shall organize the Municipal Quality Supervision Station, design unit, geological survey unit and supervision unit, Construction units and other relevant personnel in _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Verb (abbreviation of verb) project schedule control

According to the requirements of the contract, this project should be completed on _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.

VI. Project Cost Control

The project within the scope of the contract shall be constructed according to the contract and construction drawing; For the projects added by the owner or the projects with design changes, the quantities and expenses shall be controlled by the owner.

Seven, this project with the strong support of the construction unit, with the cooperation of the relevant units, supervision unit supervision according to law.

The requirements of the contract, fulfill the supervision obligations, complete the supervision work.

Supervision Construction Summary Report 3

I. Overview of the Project

Our supervision company undertook the supervision task of Donghu International Conference Center in August. The project is invested and constructed by the provincial government. Located in Donghu Hotel, the project consists of three single projects: banquet center, guest room center and conference center. The building area is banquet center12,263 square meters, guest room center 24,205 square meters and conference center 30,967 square meters. The total height of the banquet is 27.30 meters; The total height of the guest room is 20.95 meters; The total height of the banquet is 21.769m.

Second, the general situation of supervision

(1) Organization of Project Supervision Department

According to the supervision scope and control objectives stipulated in the entrusted supervision contract, and considering the age and professional level of the supervisors, our company has set up a capable supervision team to carry out on-site supervision. Project supervision department * * * has 9 members, and the organization form is as follows:

Director: 1, Director's Representative 1, Information Officer 1, Supervisor 1, Installation Engineer 2, Civil Engineer 3.

(2) Supervision system

According to the requirements of supervision planning and supervision rules, the project department, under the auspices of the chief supervision engineer, has formulated various rules and regulations such as supervision regular meeting system, post responsibility system for supervisors, on-site supervision system, file management system and succession system. , and posted on the wall, urging all members to work hard and do their duty for the owner.

1, each major arranges special personnel to fill in the supervision diary according to the building number every day.

2. The professional supervision engineers patrol the construction site four times a day (twice in the morning and twice in the afternoon) to supervise the whole process of key working procedures and key parts, and the project supervision department implements the night duty system.

3. On the 5th of each week, the director or the director's representative will organize a regular supervision meeting to summarize the completion of last week's work plan, arrange next week's work, coordinate and solve contradictions and problems in the work, and focus on solving outstanding key problems.

4. The director or the director's representative shall organize the preparation of monthly supervision report, summarize the supervision situation of each major this month, and report to the owner and the company in time.

5, each professional appoint someone to be responsible for the preparation of supervision data in the industry. Designate a special person to manage the engineering documents issued by the company and the owner, as well as the instruction documents issued by the contractor, and form a document receiving and dispatching record for future reference.

6, the project supervision department under the auspices of the director or the director's representative every quarter by professional stage supervision work summary; After the completion acceptance, make a comprehensive summary of the whole process of supervision.

(III) Internal management system of the Project Department

1. On the wall of the office of supervision department, there are system boards such as Post Responsibility System for Director and Supervision Engineer, Professional Ethics Code for Supervision Engineer, Quality Control Procedure and Schedule Control Procedure to guide the supervision personnel to work in an orderly manner. A bulletin board should be set up, and a special person should be responsible for including all kinds of rules and regulations, address books of engineering-related personnel, notices and other engineering information into the column.

2. All supervisors of the project department shall wear safety helmets with company logo when they enter the site for work.

Third, the working methods and principles of the project supervision department

After the project supervision department entered the construction site, the professional supervision engineer of the project supervision department headed by the chief supervision engineer started from the reality of the project construction, followed the principles of implementing relevant policies, strictly fulfilling the entrusted supervision contract of the construction project, and conscientiously implementing relevant technical standards, norms and laws and regulations, taking the construction of high-quality projects with reasonable investment and fast speed as the control goal, taking "law-abiding, honesty, fairness and science" as the industry standard, and taking the guidance in advance as the guidance. At the same time, Supervision engineers of all disciplines strictly exercise the rights entrusted by the Construction Supervision Entrustment Contract in their work, strictly supervise according to law with excellent professional knowledge, pragmatic and dedicated spirit, meticulous scientific attitude and fair and honest work style, constantly strengthen the internal organization and management of supervision work, actively explore and sum up work experience, and make supervision work truly reflect its scientificity and impartiality.

In terms of serving the owner, the supervision department should try its best to meet the requirements of the owner within the supervision scope stipulated in the supervision contract and strive to become the owner's staff and agent. In the management of contractors, the principle of "supervision, help and promotion" is adopted to carry out the work, and at the same time, the contractor is urged to implement total quality management to promote the management level of engineering construction to a new level.

Supervision Construction Summary Report 4

With the passage of time, 20 years passed quickly. At the end of this year, I will review my work in the past year, calm down and sum up my achievements and gains, find out my shortcomings, which will be beneficial to my future work and sum up my work in the past year. I sincerely hope that you will give me tips on improper summary, which will help me a lot. In the past year, with the strong support and care of the leaders of the company and the project department, I earnestly adhered to the "pre-control, standardized, scientific and high-quality work guiding ideology firmly established" to ensure the satisfactory service purpose of every owner and work hard wholeheartedly. 20 _ _, tell me about my work.

First, the quality control of engineering construction, control the work done in advance, after receiving the engineering design and construction drawings, I will first be familiar with the drawings, understand the design intent, understand the main technological process and engineering characteristics of the construction process, record the suggestions on the construction drawing paper in writing, take corresponding measures to apply to the construction site, and do a good job in sampling data of related projects.

Second, record and inspect all materials, personnel and mechanical equipment on site, and prevent unqualified materials from being used in the project. For the construction of key parts of the project, arrive at the station in advance, check whether the construction preparation work is in place, and make a written record of the whole construction process.

Three. Inform the project management department of the construction unit in oral or written form of the problems found in the "patrol inspection" in each construction process, and report to the resident supervision engineer, supervise the construction unit to carry out rectification and recheck, and do a good job in on-site supervision. 4. In terms of safety and civilized construction control, I have accumulated some experience through studying the safety production law and establishing the viewpoint that safety prevention is the priority, that is, work should be done first, because accidents can be prevented but unpredictable, and corresponding inspection systems should be established, such as checking whether full-time security officers are in place, checking the safety protection net at the project site, and checking the safety belts of workers working high above the ground. Safety helmet refers to whether the safety protection tools are complete, check whether the safety warning signs are set in the key parts of the site project, and rectify the safety hazards in time when they are found. Supervisors have an unshirkable responsibility for the safety of the construction site, do a good job in daily safety inspection, supervision and management, make corresponding data records, strengthen patrol work, strengthen process control, and do their work better and more seriously.

20 _ _ _ years of work is busy and full. In order to perform supervision duties, work actively, obey the arrangement of leaders, never shirk, and think of the project wholeheartedly, in the next 20 _ _ years, I will study professional business knowledge more attentively and strive to provide effective benefits for the company.

Supervision Construction Summary Report 5

I. Overview of the Project

_ _ county government business building project has a building area of 8492.64m2, a building height of 19.2m and a five-story frame structure, and is a multi-storey public building. The design life of the building structure is 50 years, the safety level is Grade II, and the seismic fortification is classified as standard fortification (Grade C). The basic design level is Grade C. ..

At present, the foundation project of _ _ county government office building started on April 6th and has been completed. At the end of July, the main structure was capped, and the second and third floors of masonry were basically completed. According to the progress of the project, the masonry of the whole project was completed this year 10. Part of plastering and part of installation works will be completed by the end of this year.

Main building structure of _ _ county cadre turnover housing project: it is a four-story frame structure with a total construction area of1965.24m2, and it is a multi-story public building. The reasonable design life of the building structure is 50 years, the safety level is Grade II, the seismic fortification crack is Grade VII, and the foundation design level is Grade C. ..

_ _ County cadre turnover room started on July 6th, the foundation excavation has been completed, and the foundation pile caps and foundation frame columns have been completed. It is expected that the foundation will be completed by the end of July, the main body will be capped before mid-September, and the infilled wall and local plastering will be completed before mid-October/kloc-0.

Second, the supervisor's work.

According to the requirements of the supervision service contract, after the two parties signed the supervision entrustment contract, the overall objectives of project quality, progress and investment supervision were determined, and the project supervision department was established. According to the supervision contract and the Code for Supervision of Construction Projects, the list of supervision projects is decomposed, and the responsibilities of the chief supervision engineer and professional supervision engineer are defined. Make the supervision work institutionalized, standardized and standardized to ensure the smooth implementation of the supervision task.

With the strong support of the owner and the company, the supervision of this project is progressing smoothly. In the whole supervision project, we strengthened and standardized the management of the supervision itself, strictly implemented various rules and regulations, and ensured the project quality and the earnest performance of the contract.

At the same time of strict supervision, in view of the problems existing in project construction and management deficiencies. Intensified the intensity of "strict supervision" and strengthened the power of sideline patrol; More reasonable suggestions were put forward, and "prior supervision" and "active supervision" were strengthened. In the process of supervision, 100% of concealed works and key parts are in a wait-and-see state, and they are checked repeatedly at ordinary times to nip the engineering quality problems in the bud.

Third, the project supervision and management

Examination and approval of the overall commencement report and the commencement report of sub-projects: Our supervision department will examine the contractor's labor, materials and machinery input, the rationality and feasibility of the construction scheme, the concrete measures to ensure quality and the construction of the contractor's quality inspection system in strict accordance with the requirements of ensuring the construction period and quality and meeting the contract conditions.

The handover of sub-projects is the focus of supervision's daily work and quality control of engineering construction. The supervision department shall conduct a comprehensive inspection of the previous working procedure first, and confirm that it meets the relevant requirements after treatment, before it is allowed to move to the next working procedure.

The supervision department conducted a strict inspection on the ex-factory certificate, model, specification and ex-factory date of the materials entering the site for this project. After the arrival of raw materials, the contractor shall conduct re-inspection and supervision sampling inspection in strict accordance with the specified batch, so as not to miss the inspection, and make clear the parts where the materials are used.

The problems found by the station and patrol should be notified orally at the scene in time, requiring the construction unit to rectify. If the problem is serious or the contractor fails to make rectification as required, the supervision department will issue a notice to the supervision engineer. All the quality problems found were rectified under the supervision of the regulatory authorities and ordered to be closed.

Fourth, the project schedule management

Overall construction progress plan, phased construction plan and monthly construction plan reported by the construction unit. The supervision department has comprehensively considered the requirements of the contract period and the principles conducive to the project quality. In view of the reasonable input of labor, materials and machinery required to complete the plan, to ensure the construction plan and quality assurance of the contractor's planned completion, the supervision department made a reasonable adjustment reply after detailed examination. When the construction period is tight, the construction unit is required to reverse the construction period, and the contractor is required to invest the necessary equipment, manpower, material resources and financial resources, organize scientifically and manage strictly to ensure the normal progress of the construction.

Verb (abbreviation of verb) clean government construction and safety management

The supervision department actively follows the requirements of the owner and superior departments in the aspects of clean government construction, civilized construction, safety and environmental protection. And organize relevant meetings regularly, so that every supervisor can work honestly and fairly. Monitor the implementation of safety measures and the results of rectification. Up to now, there have been no safety accidents in this project.

In short, in the construction supervision work, we have grasped the important parts and key links, put prevention first, and always strictly control to ensure quality. The project is safe and reliable, and meets the design and specification requirements. We will correct the existing problems in time with a rigorous and pragmatic working attitude, overcome the ineffective factors, intensify our work, and hand in a satisfactory project answer sheet for the owner!

Related articles of supervision construction work summary report:

★ Model essay on summary of construction project supervision work

★ 5 Summary of construction project supervision.

★ 5 summary papers of engineering supervision.

★ Five selected model essays on the builder's work summary report.

★ Summary report of project supervision work

★ The supervisor summarizes five model essays.

★ Annual Work Summary of Project Supervisor

★ 5 Summary of supervisor's personal work.

★ Five selected annual work summaries of on-site supervision in 2020.

★ Five summaries of the project supervisor's annual work.