Simplification of the right side of 480/X-4=480/ 4X/3 equation
480/X-4=360/X shift term subtraction
(480-360)/X=4
4X= 120
X=30
Test: substitute X=30 into 480/x= 16.
So X=30 is the solution of the equation.
Solution: The original plan took 4 days longer than the actual task, and the number of days required in the original plan was 480/X, because the actual factory was 1/3 more than the planned factory, so the actual factory was (X+X* 1/3), which can be obtained.
I plan to plant 30 trees every day.