2. Laying gas pipeline. It is planned to lay120m every day and complete the task in 20 days. Because the residents are in a hurry to use it, the superior requires laying 25% more every day, so how many days in advance can the task be completed?
Solution: 56*( 1- 1/8)=49 people.
Solution:120 * 20120 * (1+25%) =16 days.
20- 16=4 days
Finish 4 days ahead of schedule