B it takes b days to complete this project, and it costs y yuan every day.
4/A+ 15/B= 1
4X+ 15Y=420
8/A+(B- 10)/B= 1
8X+(B- 10)Y=440
By solving the above equations, we can get: A= 16, B=20, X=30, Y=20.
1. It takes Party A and Party B 16, 20 days to complete this project.
2. Party A and Party B each need 480 yuan to complete this project, and 400 yuan.
3. Set M days for Party A and N days for Party B..
M/ 16+N/20= 1
m+N & lt; = 18
Cost =30M+20N=400+5M
It is equivalent to finding the minimum value of m (if you have studied linear programming, you should use its method to do this problem, if not, you can simply analyze it)
Because N=20-5M/4, so
m+N & lt; = 18 is equivalent to 20m/4.
So A works at least 8 days.
4. Let's choose one of the three.
M/ 16+N/20= 1
30M+20N & lt; =430
Solution: m
So A works for six days at most.