=( 1-20/40)/50= 1/ 100
1/( 1/ 100)= 100
It takes 100 days for Team B to finish alone.
2)
x/40+y/ 100= 1
y= 100-(5/2)x
y & lt70, 100-(5/2)x & lt; 70,x & gt 12
12 & lt; x & lt 19
x= 14, 16, 18
***3 sets of reasonable schemes to choose from.
3) x= 14, y=65, and the project cost =14 *1.5+65 *1= 86.
X= 16, y=60, and the project cost =16 *1.5+60 *1= 84.
X= 18, y=55, and the project cost =18 *1.5+55 *1= 82.
For the scheme with the least project cost, the construction period of team A is 18 days, and that of team B is 55 days.