The work efficiency is improved by 25%, that is, the original: 1+25%=5/4, and the time is 4/5. Results The task was completed two days ahead of schedule, and the original time was 2/( 1-4/5)= 10 days.
Therefore, the original production time of 16000 was: 18- 10=8 days, and the original plan was to produce 16000/8=2000 pieces per day.
Then, the task of this batch of production is: 18*2000=36000.