Mathematical problems in Xiaoshengchu's summer homework
1. As can be seen from the figure, there is only one black tile in the middle row, so the number of rows and columns of this layer of tiles is (77+ 1)/2=39. So the number of white tiles is 39*39-77= 1444.

If you want to finish the work as soon as possible, of course, you should choose the one with fewer working days, so you should go to team A and team B first.

1/(110+115) = 6 days.

It will be finished in six days.

A's salary is 6 *18 =10.08 million yuan.

B's salary is12 * 6 = 720,000 yuan.