Answer and analysis:
When you encounter such a problem, you have to assume that a person does a job a day.
Then the total number is 1× 20× 15 = 300-20 people 15 days ***300 copies.
If actual days are required, actual days =3+ remaining days.
So we must first find the remaining days, and the remaining days = remaining copies/number of people.
The rest of the day's work was completed by 20-5= 15 people.
Remaining parts = total parts 300- dried parts
I did it for three days, and 20 people did it every day for three days, so I made 1×3×20=60 copies.
300-60= 240 copies left.
Days remaining =240/ 15= 16 days
Actual days = 16+3= 19 days.
This process assumes that everyone does a job.
1×20× 15=300 copies-total
1×3×20=60 copies-60 copies have been made.
300-60=240 copies-the remaining copies.
240/(20-5)= 16 days-remaining days.
16+3= 19 days-actual days.