Safety construction agreementNo. 1 main contract:
Party A (Owner): Xinjiang Hongyuan Shengtong Electric Power Engineering Co., Ltd.
Party B (contractor):
According to the agreement, in order to implement the policy of "safety first, prevention first", clarify the safety responsibilities of both parties, and ensure the safety of people, buildings and equipment during the construction process, Party A and Party B signed this agreement through consultation in accordance with the People's Republic of China (PRC) Safety Production Law and other relevant national laws and regulations.
The first project:
Construction address: changji city High-tech Zone Industrial Park.
Project content and scope: all services undertaken by the contractor in the installation project.
Commencement date: June 28th, 20xx (subject to the approved commencement report)
Completion date: August 28th, 20xx
Article 2 Safety objective: put an end to major accidents and illegal command and operation.
Article 3 Party A's Safety Responsibility
1. Before the commencement of construction, Party A shall review Party B's ability to undertake the safe construction of this project, make a comprehensive technical disclosure to Party B, and disclose the safety management requirements of facilities and equipment in this unit and this construction area, with written records or materials.
2. Party A shall require Party B to formulate construction safety measures and report them to Party A for the record. Party A shall review and supervise the implementation of construction safety measures formulated by Party B when working in dangerous production areas.
3. Party A shall designate a special person to be responsible for contacting, inspecting and coordinating Party B to implement relevant safety regulations.
4. Party A has the right to stop and correct the problems existing in Party B's safe and civilized construction, and issue a safety rectification notice.
5. Party A has the right to spot-check the safety technical knowledge and safety working procedures of the personnel involved in the construction by Party B. ..
6. Party A is responsible for investigating and reporting Party A's accidents during construction.
Article 4 Party B's Safety Responsibility
As the contractor of this project, Party B shall take full responsibility for personal injury, equipment and engineering quality accidents, site fires and all man-made accidents caused by its own mismanagement or negligence of Party B's construction personnel, and shall not increase Party A's expenses or delay the construction progress. Party B shall earnestly perform the following safety responsibilities:
1. Party B shall ensure that the relevant qualification certification materials required for the contracted engineering services provided are true and legal.
Effective.
2. Party B must implement the national laws and regulations on production safety and formulate the corresponding safety management system; Strictly implement the Code for Temporary Electricity Consumption, Construction Safety Inspection Standard, relevant safety construction systems such as climbing, hot work, breaking ground, lowering trough (pit) and hoisting, and other safety production rules and regulations.
3. On-site construction shall comply with national and local laws, regulations and rules on labor safety and employment, and ensure the legality of employment. Party B must provide labor protection articles and safety appliances for construction personnel in accordance with relevant state regulations.
4. During the construction period, Party B shall set up a full-time safety management organization with full-time safety supervisors (those with less than 30 employees shall work part-time). Meanwhile, Party B designates _ _ as the contact person for safety work. Responsible for the safety management, coordination and monitoring of the construction site.
5. In all construction activities, Party B must prepare safety construction measures, make a comprehensive safety technical disclosure to all construction personnel before construction, and implement them correctly and completely during the whole construction process. Construction is strictly prohibited without measures or disclosure.
When working in dangerous areas that may cause fire, explosion, electric shock, poisoning, suffocation, mechanical injury, burns, power failure or production equipment shutdown, special guardians must be appointed, and special construction safety measures must be formulated, which will be supervised and implemented after being reviewed and approved by Party A. ..
6, large independent construction projects should also prepare the construction organization design, and supervise the implementation after Party A and the supervision unit have passed the examination.
7. The construction machinery, tools and safety protection appliances used by Party B for this project must meet the construction needs, meet the safety requirements after inspection, and be inspected and maintained regularly during the construction process.
8. Before the project starts, Party B shall organize all construction personnel to carry out safety education and safety inspection by departments, and report the list of qualified personnel (including temporary supplement or replacement) and inspection results to Party A for the record. Special operations personnel must hold qualified and effective qualification certificates issued by relevant departments.
9. Before starting work, Party B shall organize personnel to inspect the construction area, working environment and the use of facilities, equipment and tools provided by Party A to confirm that they meet the safety requirements. Once the construction is started, it means that Party B confirms that the construction site, working environment, facilities, equipment and tools meet the safety requirements and are in a safe state.
10. Party B shall not carry out construction beyond the designated construction scope, and set up temporary fences or warning signs within the construction scope to prohibit irrelevant personnel from entering the construction site. Without the consent of Party A, Party B shall not use Party A's facilities and equipment unrelated to construction without authorization; Party A's protective facilities and signs shall not be removed or changed without authorization.
1 1. Party B must accept the supervision and inspection of Party A, and make timely rectification and feedback the safety rectification opinions put forward by Party A.
12. Party B shall immediately report to Party A the accidents or unsafe conditions that endanger the production and operation during the construction, and actively cooperate with the investigation. At the same time, the personal casualty accidents of Party B's personnel in the construction process must also be reported to the local government's safety management department, public security department and trade union for investigation and handling, and Party B will report them centrally.
13. In case of personal injury, equipment damage, fire and other accidents caused by Party B during the construction process, Party B shall bear all responsibilities and compensate all economic losses of Party A..
Article 5 Liability accidents related to this project caused by a third party shall be solved by the parties themselves.
Safety accidents caused by force majeure natural disasters shall be settled by both parties through consultation; Party B should have foreseen, or had foreseen, the safety accidents without taking preventive measures, and Party B shall bear all the responsibilities.
Article 6 Contact information and reply time of Party A and Party B: Party A and Party B shall communicate with each other in the form of work contact sheet, fax, telex and other written forms. After receiving the written contact from the other party, both parties shall respond within 8 hours.
Article 7 Construction security deposit
After the project contract is signed, Party B shall pay a deposit of 5,000 yuan to Party A before the project starts. During the construction, Party B did not violate the safety management regulations, and no personal injury, equipment and above accidents occurred. After the project is completed and accepted, Party B will refund the deposit in full (excluding interest); In case of any of the following circumstances during construction, the corresponding deposit shall be deducted:
(1) In case of serious injury or above, personal accident, fire, collapse, hoisting and major equipment accident, all safety deposit shall be deducted;
(2) Personal injury accident, fire, collapse, hoisting and equipment accident, 50% safety deposit shall be deducted;
(3) Anyone who violates the safety management regulations will be fined 100-200 yuan.
Article 8 Liability for breach of contract
1. The qualification certificate provided by Party B is invalid, and Party A has the right to terminate the contract, and all losses caused thereby shall be borne by Party B..
2, in violation of laws, regulations, rules and the provisions of this agreement, resulting in construction safety accidents, in addition to accepting the relevant government departments to deal with, the fault party should bear the liability for breach of contract of 1000 yuan/person.
3. Party B fails to establish a safety management organization and correctly and comprehensively implement safety technical measures and construction organization design; Construction personnel did not grasp the characteristics of the project and construction safety measures; If the construction machinery, tools and safety protection appliances used in this project can't meet the construction needs, Party A has the right to ask Party B to stop work immediately for rectification, and the consequences and losses arising therefrom shall be borne by Party B. ..
4. If Party B's personnel fail to pass the sampling test specified in safety work or special personnel take up their posts without a license, Party B shall bear the liability for breach of contract of 100 yuan/person.
5. If Party B uses the facilities, equipment and tools provided by Party A to cause damage, it shall pay compensation according to the price.
6. Party B's personnel go to other production areas without reason or use Party A's facilities and equipment without authorization, which has not caused consequences. Party B shall be liable for breach of contract at the rate of RMB 65,438+000 per person.
7. If Party B fails to rectify the safety rectification opinions put forward by Party A in time, Party B shall bear the liability for breach of contract of 100 yuan/day for each day overdue.
8. In case of personal injury, fire, collapse, hoisting and equipment accidents in the construction process, the party at fault shall bear the liability for breach of contract of 50,000 yuan/time, in addition to being handled by relevant government departments.
Article 9 Other matters agreed by Party A and Party B:
65438+
If the same person violates the rules for the second time, the punishment will be doubled one after another.
3, the implementation of fixed management, ensure the fire escape, civilized construction.
Article 10 In case of any dispute during the execution of this Agreement, both parties shall settle it through negotiation and mediation. If the dispute cannot be settled through negotiation or mediation, both parties agree to bring a lawsuit to the people's court where the project is located.
Party A and Party B must strictly perform this agreement, and the legal effect of this agreement is independent of the main contract.
The term of validity of this agreement: 20xx May 28th to 20xx1February 30th (the term of validity of the safety liability is from the effective date of the independent contract to the expiration of the warranty period).
This agreement shall come into force after being signed and sealed by the legal representatives or entrusted agents of both parties.
This agreement is made in quadruplicate, with each party holding two copies.
Article 11 The following items 1-7 are annexes to this agreement.
1. Relevant qualification certification materials required for contracting projects.
2. Relevant certification materials of Party B's construction technicians and work leaders.
3, special operations personnel qualification certificate
4, Party B's construction personnel safety technical knowledge and safety work procedures test report.
5, construction safety technical organization measures
6, large independent project construction organization design
7, construction safety technical disclosure
Party A (seal): Xinjiang Hongyuan Shengtong
Power Engineering Co., Ltd. Party B (seal):
Authorized Agent: Authorized Agent:
Tel: Tel:
Signing place: meeting room of Xinjiang Hongyuan Shengtong Power Engineering Company
Signing date: May 28th, 20xx.
In order to ensure the fire safety during the decoration, according to the relevant regulations of xx municipal government, the fire safety responsibility system is implemented step by step in the decoration project area. At present, the Property Management Office (Party A), the owner (user) and the decoration construction unit entrusted to carry out the decoration project (with Party B) have entered into a power of attorney on fire safety as follows:
Party A's responsibilities:
1, supervise the decoration project according to the design scheme approved by the fire department;
2. Coordinate Party B's construction mobilization;
3. Be responsible for introducing the residential fire protection facilities and relevant laws and regulations related to this project to Party B;
4. Be responsible for coordinating the electricity, water and heat work of Party B during the construction period;
5. Have the right to supervise the fire safety during Party B's construction, and have the right to order Party B to make corrections until it is ordered to stop working, and report to the relevant departments for handling according to law.
Party B's responsibilities:
1, responsible for the fire safety responsibility of the renovation project of residential units to ensure that no fire accident occurs.
2. Set up the person in charge of site safety (name:) to learn about the fire safety of construction from Party A and be responsible for the fire safety of construction.
3. Electricity, water and hot work shall be approved by Party A before:
3. 1 The electrical operator shall hold the electrician operation certificate, show the original and copy to Party A for the record.
3.2 When hot work is carried out, Party A's hot work permit shall be obtained in advance, and it shall be operated by a certified welder. Illegal operation is strictly prohibited.
4. Party B shall abide by the management systems of Party A..
5. When Party B needs to use flammable materials in the construction, it must keep the flammable materials well in advance and report to Party A by a special person. It can only be brought in after Party A's approval, and the designated counter is responsible for it. Don't store too many items, limited to the amount used that day. After the construction is completed, the remaining items must be taken away from the site.
6. Smoking is prohibited in the construction area.
7. The construction area should be equipped with fire fighting equipment, and the number of portable fire extinguishers should be at least two.
8. Deal with the fire accident in time, notify Party A in time and call 1 19 to truthfully report the cause of the accident, protect the site and cooperate with the investigation.
9. On-site decoration garbage should be cleaned up to the designated area in time, especially shavings and sawdust should be cleaned up every day, and designated persons should be responsible for it. It is forbidden to block the fire escape with construction waste or garbage, and it is forbidden to block, damage or misappropriate fire control facilities to ensure the cleanliness of the site.
10. When off duty, Party B's construction personnel should carefully check the construction site to prevent fire hazards and cut off the power supply of electrical equipment when leaving.
1 1. Party B shall conduct safety education for construction personnel, actively cooperate with Party A's supervision and inspection, and formulate a safety system. This agreement is made in triplicate, one for each party.
Party A (property service enterprise):
Party B: (Owner) (Decoration Construction Unit)
Year and day
Article 3 of the Safety Construction Agreement Party A: XX (hereinafter referred to as "Party A")
Party B: XX (hereinafter referred to as "Party B")
In order to strengthen the safety management of xxxxxx and ensure the safety of lines and electricity consumption, Party A and Party B hereby enter into a safety agreement through consultation.
I. Responsibility of Party A
1. Party A shall conscientiously implement the Law of People's Republic of China (PRC) on Work Safety, the Law of People's Republic of China (PRC) on Electricity, relevant regulations of government departments and Party A's management requirements for safety work.
2. Party A shall conduct pre-job professional training for Party B, and be familiar with the power line distribution map of the unit. Party B can only enter the distribution room of Party A for operation after passing the training and examination.
3. Party A shall pay attention to safety precautions such as working environment and key parts, and provide a safe and standardized operating environment for Party B. If there are hidden dangers that need to be solved by Party A, Party A shall bear all responsibilities for any personal injury or economic loss caused by unsafe accidents.
4. Party B shall make every effort to solve related safety problems.
II. Responsibility of Party B
1. Party B must hold relevant certificates issued by the state, strictly abide by operating rules and regulations, and shall not operate illegally.
2. Party B shall conscientiously implement the Safety Production Law of People's Republic of China (PRC), the Electricity Law of People's Republic of China (PRC), the relevant regulations of government departments and the safety management requirements of Party A's company, and strictly abide by various safety management regulations.
3. Party B shall be on call if there is any problem, and shall not leave his post or find someone to replace him during the operation, and make a good record registration to ensure the safety of the operation.
4. Party B's personnel shall not use or dismantle the electrical facilities of Party A's unit without permission, and must equip and use qualified professional electrical tools (inspected by relevant departments) during their work, otherwise, Party B shall bear all the responsibilities for any accidents and economic losses caused by the casualties of Party A, Party B and the third party operating illegally, and Party A shall not bear any responsibilities.
Three. Matters not covered in this agreement shall be handled in accordance with national laws and regulations. In case of any conflict between this Agreement and national laws and regulations, the latter shall prevail.
Four. This agreement is made in duplicate, one for each party.
Verb (abbreviation of verb) This agreement shall be implemented as of the date of signature and seal.
Party a: XX
XXXX,XXXX,XX,XX
Party b: XX
XXXX,XXXX,XX,XX
Article 4 of the Safety Construction Agreement Party A: Laohekou Xinjing Technology Co., Ltd.
Party B: person in charge of equipment, facilities and pipeline insulation:
1. Purpose: In order to safeguard the common interests of Party A and Party B, ensure the construction quality and safe production, and maintain a good working order and a safe and hygienic environment on the construction site, Party A and Party B have entered into this safety construction agreement through equal consultation.
Second, the construction period: year month day to year month day.
Three. Agreement content:
1. When Party B enters the factory for construction, it must be approved by the person in charge of Party A, and the person in charge of on-site construction shall be appointed, and safety supervision shall be set up at the construction site to facilitate coordination and contact during construction; At the same time, Party A shall provide convenient construction conditions and services for Party B on the premise of not affecting Party A's safe production and operation.
2. Before construction, Party B must give safety education to the construction personnel, and sign a safety construction agreement with Party A. Without the safety agreement, construction may not start. After obtaining Party A's project, Party B shall not subcontract it to other construction teams. If Party A confirms that the project is subcontracted, Party A may request to stop work or cancel Party B's construction right, and find another supplier to cooperate.
3. Before starting work, Party B must formulate a safety construction plan, safety precautions and emergency measures, and report them to the safety supervision and management department of Party A for the record.
4. Party B's construction personnel must wear labor protection articles and safety protection articles strictly when entering Party A's factory, and special operators must also hold relevant certificates.
5. Party B shall set up obvious warning signs in the construction area and close the centralized construction projects for a long time. Construction personnel shall be active in the construction area, and shall not enter the non-construction area at will, and Party A's personnel shall have the right to check at any time.
6. The safety protection equipment of Party B's construction team must be equipped in place and the safety measures are effective, otherwise the operation shall not be started; Party B shall be responsible for any accidental personal injury or accident loss caused during the construction.
7. If water and electricity are needed in the construction process, Party B must apply in writing, and with the consent of the person in charge of Party A, the professionals will designate the water and electricity connection places, and ensure the electrical wiring and pipeline connection specifications.
8. In the process of construction, if there are special operations, such as climbing and hoisting, safety protection articles and facilities, such as scaffolding, safety belts and safety helmets, should be equipped in strict accordance with the requirements of special operations, otherwise operations may not be carried out.
9. The speed of construction vehicles entering the factory shall not be greater than 5km/h, and must be checked by the guards on duty before leaving the factory. The articles carried with the vehicle must be signed by the responsible persons of Party A and Party B before they can be released.
10. During the construction process, Party A implements the supervision and inspection system, and has the right to inspect at any time, stop illegal operation, punish the behavior violating safety regulations or order the construction team to stop work for rectification.
1 1. The garbage generated by Party B in the construction process must be cleaned up on the same day. After the construction, the construction site should be thoroughly cleaned, so that the work is finished, the materials are exhausted and the site is cleared. Properly dispose of the cleaned garbage, and Party B shall be responsible for the pollution and traffic accidents caused thereby.
12. Other outstanding matters shall be settled by both parties through consultation.
6. This agreement is made in duplicate, each party holds one copy, which has the same legal effect. This agreement shall come into force as of the date of signature (seal) by both parties.
Party A (official seal)
Party B (official seal)
On behalf of:
On behalf of:
date month year