Time goes by, never stops, and a piece of work is over. Looking back on your work during this period, I believe you have many feelings. You might as well sit down and write a work summary! Before writing, you can refer to the model essay. The following is a summary model essay (5 selected model essays) of the work of the construction unit compiled by me for your reference, hoping to help friends in need.
Work Summary of Construction Company 1 20xx is a year of project management for construction enterprises, and it is also a year facing financial crisis. We should learn and carry forward the Olympic spirit of "Faster, Higher and Stronger" with practical actions, seize the opportunity, establish a high sense of responsibility, and formulate practical measures to ensure the company's good business performance and sustained and effective development. Summary of our work:
First, promote project management and improve construction and production.
1. Grasp two key points and do a good job in the project. Anticorrosion of ethylene underground pipeline and Qingdao Refinery are listed as the key projects of the company in 20xx, and all work is done around the key projects.
The first is to strengthen project preparation. According to the scope of the project, the characteristics of the project, the particularity of the process, and the requirements of the general contractor and the owner, a specific plan should be formulated to improve the operability of the project. Each project department must carefully analyze the characteristics of the project, make targeted preparations, and balance and coordinate various resources from five aspects: people, machines, materials, methods, environment and testing (testing) to lay a good foundation for ensuring the smooth implementation of the project.
The second is to strengthen process control. It is necessary to make overall arrangements, carefully organize, optimize the construction scheme, rationally arrange the working procedures, strengthen dynamic management, care about customer needs, and fully complete the annual construction and production tasks. Finally, do a good job in project summary. Each project department should strengthen the accumulation of process data, actively organize a comprehensive summary of completed projects, summarize and analyze the experiences and lessons in the construction process, and really play a reference and guiding role in construction summary.
2. Strengthen project management and improve project management level.
First, it is necessary to improve the construction of execution and carry out construction and production in strict accordance with the project management manual.
The second is to enhance the awareness of project accounting.
The company will strengthen management, give the project greater power, tap the management potential, lay a solid foundation for promoting the company to gradually develop from a construction-oriented enterprise to a management-oriented enterprise, and build a management brand with Jialong characteristics through standardized management.
Second, market-oriented, improve market share.
In 20xx, the company has made remarkable achievements in market development, and established a certain reserve for the construction and production in 20xx-Tianjin comprehensive ground pipeline anticorrosion has undertaken more than half of the project share; Tianjin 28th Bureau, Nanjing No.2 Company, Qingdao, Fujian, Sichuan and other pipeline groups all have our projects. Chengdu PetroChina's new 36 billion integration project is under negotiation; Shot blasting has formed a large-scale production capacity and so on. To sum up, it shows that the company has obtained sufficient construction tasks this year, and Tianjin integration will reach a climax next year, which indicates the good development trend of the company this year and next.
1. Based on the traditional market, strive to expand the external market. The situation is gratifying, but increasing market share is still the eternal goal of every enterprise. Focus on key projects as key tracking projects, pay close attention to the signing dynamics of projects, fully track information, and strengthen multi-level communication with general contractors and cooperation units. It is necessary to take the opportunity of ethylene underground pipeline anticorrosion and Qingdao Refinery to do a good job in the follow-up projects and the expansion of surrounding markets.
2. Build an information network and strengthen the collection and processing of market information. Actively track information inside and outside the industry, scientifically apply bidding experience, properly apply bidding skills, strengthen the quality of bidding documents, and improve the winning rate.
Third, strengthen basic management and build a leap-forward development platform.
1. Constantly improve various management methods and plug management loopholes. It is necessary to strengthen the operation management of the quality system, improve the supervision and inspection system of site safety, quality, materials and equipment, and continue to formulate and improve the company's income increase and expenditure reduction.
2. Solve the bottleneck of market access and improve the qualification. Starting from the company's market development strategy, we must first solve the market access problem. The current qualification status of the company cannot meet the development requirements of the company. This year, the company should cooperate with each other, do a good job in applying for relevant qualifications, prepare upgrade materials and improve the company's relevant qualifications.
3. Strengthen procurement and supply management and strictly control material costs. First, rectify and improve the supplier system and standardize the procurement channels of materials and equipment. Second, adhere to the principle of shopping around and purchase common materials from manufacturers to reduce the cost of material consumption.
4. Strengthen human resources work. First, improve the human resources information network, absorb the social resources reserve resources, and select a powerful construction team to be included in the company's resource list. The second is to strengthen training, do a good job in the study and education of laws, regulations and technical skills, and improve the quality of all staff.
5. Continue to strengthen self-construction. Do a good job in the construction of Anda base and Hainalong.
Fourth, create a corporate culture with the characteristics of "Jialong"
Corporate culture construction is the catalyst of enterprise development, and it is also the basis of improving enterprise cohesion and social evaluation. Creating a corporate culture with "Jialong" characteristics is our eternal theme.
1. Strengthen training and build a learning enterprise. Ensure that the training time for the operation layer is 72 hours and the training time for the management layer is 48 hours.
2. Actively participate in various social welfare activities.
3. Continue to increase outstanding employees who pay social insurance.
4. Do a good job in visiting and condolence activities for vulnerable groups and build a harmonious enterprise.
Summary of the work of the construction unit II. Overview of the project:
Combined with the actual situation of school construction, it is determined to build a cement road with a length of 1 13m, a width of 3.5m and a thickness of 0. 18m. The project cost is 27,600 yuan.
Second, the general layout of the construction, the total schedule and the main quantities completed:
1, construction organization
In order to do a good job in the construction of this project, the company sends experienced, good management and strong sense of responsibility management and technical personnel to form the construction project management department. The project manager intends to implement the project manager responsibility system, manage construction projects in a unified way, monitor quality and progress in a unified way, coordinate social relations in a unified way, and ensure logistics supply in a unified way. On the premise of ensuring the quality and progress of the project, fully reflect the company's benefits and strive for a win-win situation in quality and efficiency.
The Project Management Department consists of the following personnel:
The functions of each institution are as follows:
Safety production and quality inspection test group: responsible for the technical indicators of the project and the quality supervision and inspection of the whole project, and responsible for the safety inspection of the whole project site.
Engineering technical group: responsible for the whole engineering technical work.
Financial accounting group: responsible for financial management and ensuring the funds needed for the project; Responsible for the cost accounting, economic analysis and project settlement of this project.
Logistics materials group: responsible for the procurement and supply of materials on the construction site and the living services of construction personnel.
2. General layout of construction
1) The construction layout follows the principles of adjusting measures to local conditions, adapting materials to local conditions, facilitating production, life, management, safety, feasibility and economy.
2) The construction layout should be gradually formed according to the construction needs and along with the construction progress, so as to meet the construction needs of each paragraph and be connected before and after.
3) The construction layout should be compact and reasonable, save land and occupy less cultivated land as far as possible.
3, the total construction progress
The total construction progress is from August 22, 20xx to August 28, 20xx, with a total of 6 days.
4. Complete the main quantities.
1) subgrade layout is 800 square meters.
2) Cement pavement is 395.5 square meters.
Fourth, civilized construction and safe production
In order to ensure the construction of the project in a safe and civilized environment, the project department has formulated strict organizational discipline and various rules and regulations, and held regular educational activities. There were no public security incidents or casualties during the whole construction period.
1, civilized construction
The layout of each construction project is reasonable, the construction site is neat and orderly, materials are neatly stacked, safety signs are obvious, and labor discipline is strict.
The construction work is standardized, standardized and institutionalized, and everything has rules to follow. Someone is in charge, someone is supervising, and it is well documented.
The construction environment is good, the roads are smooth and smooth, the dust flying during driving is controlled, and the mechanical noise of cement dust during operation is controlled to a minimum.
2. Safe production
Improve the safety production supervision network, set up safety personnel according to the project department, construction team and team level 3, and form a leading group for safe and civilized construction with the project manager as the first responsible person.
Organize the personnel entering the site to seriously study the Building Law and relevant laws and regulations on building safety management, conduct safety production education, and do a good job in pre-job technical training.
Before construction, safety technical disclosure shall be made, special operators shall hold relevant certificates, and employees engaged in dangerous operations shall be insured against accidental injury.
In the process of construction, implement the safety measures plan, provide necessary safety protection and safety measures, carry out the construction in strict accordance with the operating specifications, and resolutely put an end to illegal operations. Safety officers often go to the site for safety inspection.
Verb (abbreviation of verb) main construction methods
After the project starts, all technical personnel, full-time quality inspectors, full-time operators and team leaders of the project should be familiar with the drawings, prepare the construction organization design and the overall construction schedule, and make technical disclosure.
According to the drawings, the foundation design data and survey marks provided by the owner or supervision engineer, the elevation shall be measured on site, and the construction control network shall be established, and the sample lines of the layout scope of temporary works shall be controlled with the same precision, so as to ensure that the layout of temporary works is convenient for construction and does not affect the construction of the main project, and to ensure the accuracy of survey and setting-out of the main project.
1, earthwork
The earthwork of this project is mainly mechanical construction, and the 1m3 hydraulic backhoe excavator is used to dig, clear the field and level the soil, and the road roller is used to compact and manually level the slope.
2, concrete engineering
Concrete engineering is mainly used for pavement.
(1) template
The fabrication and installation of formwork shall conform to the requirements of construction drawings, and the formwork structure shall have sufficient strength, rigidity and rigor.
(2) Materials
1) cement
Cement shall conform to the current national and industrial standards, each batch shall have the factory certificate, and samples shall be taken for quality inspection as required. Bagged cement shall not exceed 3 months, and bulk cement shall not exceed 6 months.
2) Aggregate
Aggregates shall conform to the specifications, and the gradation shall be determined through tests and approved by the Supervisor. All aggregates transported to the construction site shall be piled up according to the variety and origin, and inspected once every 500m3. Self-inspection is qualified, and it can be used after being checked and signed by the supervisor.
3) Mix proportion and sampling test
The concrete mix proportion of different types of structures is selected through tests, and the test method should be implemented according to the relevant provisions of sd 105-82, and reported to the supervisor for approval three days before the test. If changes are needed during construction, they must be approved by the supervisor again. In the process of concrete pouring, concrete sampling tests are carried out at the export machine and the pouring site.
4) Ordinary concrete
Before concrete pouring, the sundries, dirt and loose stones on the foundation surface shall be cleaned and drained, and the supervision shall be notified to pass the inspection before pouring. During the pouring process, the contract supervision engineer shall check and accept the survey and lofting results of concrete engineering buildings. Pay attention to embed all kinds of embedded parts as shown in the construction drawings. After pouring, cover sacks and woven bags with water for curing.
Six, engineering construction quality assurance measures
1. Conduct pre-job training for management personnel and technical personnel who enter the site, conscientiously implement the policy of "surviving by quality", and organize technical personnel to seriously study bidding documents, engineering design and relevant technical specifications, procedures and standards.
2, the project department quality director timely organize relevant personnel to carefully prepare quality control plan and construction work instruction, submitted to the supervision engineer for approval.
3. Cooperate with and obey the supervision and guidance of the supervision engineer, and strictly abide by the engineering supervision instructions issued by the supervision engineer.
4, in strict accordance with the requirements of the specification construction, construction process quality control using process management point control method. To ensure the quality of divisional and sub-divisional (unit) projects with process quality, those who fail to meet the process quality standards must be resolutely reworked until they pass the inspection before moving to the next process.
5. The project department should analyze the process quality control points before the implementation of each process, and make technical disclosure of the process quality control points to the foreman, construction captain or team leader. Foreman, construction team leader or team leader shall make technical disclosure of process quality control points to operators.
Summary of Work of Construction Unit 3 Time flies. In a blink of an eye, I have been working in Kunming for almost two years. In the past two years, at the age of 49, with the care and help of project leaders and colleagues, I have successfully completed all the work and further improved my ideological consciousness. This year's work summary mainly includes the following items:
First, theoretical research.
In my work, I am very supportive of the party's policies and guidelines. Insist on watching news broadcast TV programs every day, care about and study national current affairs and politics, apply the party's political thoughts and policies to engineering construction, and often have discussions with project department personnel.
Second, the work attitude
From the' first day' when I entered Jinjiang community, I made up my mind to work hard and finish what I started. I insist on successfully completing any hard work and making achievements, regardless of personal gains and losses. This year, the project often worked overtime to grab the construction period all night. No matter in the cold wind, hot sun or heavy rain, I stuck to my post, directed the smooth completion of various sub-projects and watched the completion of Stuta. I feel extremely proud and glorious in my heart, and countless hardships and sweat have been praised by the leaders.
Third, at work.
Every time new norms and standards in the construction industry are issued, I study and study hard, try to master the new norms, standards and quotas, and apply them to engineering construction, constantly summing up experiences and lessons. Every time the project is completed and accepted, I carefully record the project acceptance, compile it and store it in my own project completion acceptance record file. I often analyze and study the completion acceptance records to find out what problems I have in the project construction, what aspects are worth improving and what aspects are worth carrying forward.
Fourth, the project management experience
Construction project management is a complex and changeable work, and the quality of management is directly related to the economic and social benefits of the project. Engaged in management for many years, I think project management is a system of overall arrangement, rational utilization and comprehensive management. Maximize the management of safety production, adhere to the policy of "safety first", ensure the quality of the project, adhere to the principle of "survival by quality", strictly control the quality of the project, strive for fast progress of the project, abide by the construction contract, reduce the project cost, and create the project with the best quality, the safest production and the lowest project cost in the shortest time.
The construction industry is an industry with deep knowledge and wide knowledge. It can be said that it is an "old-fashioned" industry. In my future work, I will study cultural knowledge and professional knowledge harder, practice constantly, do my job well and make more contributions to society.
Work summary of the construction unit 4 1. Conscientiously implement the target responsibility of safety production.
In order to seriously implement the work spirit of higher-level safety production, our town held a working meeting at the beginning of the year to decompose and implement the safety construction objectives and responsibilities step by step and implement them layer by layer. Implement the responsibility of safety objectives to the front line.
The second is to strengthen the inspection of safety construction.
In order to strengthen the supervision of safety construction, our town insisted on carrying out safety construction inspection according to the actual situation, and issued the "Construction Safety Work Plan", which made a comprehensive deployment of the inspection work. Through the inspection, we not only mastered the safety production management of each building, but also issued a rectification book for those with potential safety hazards, requiring immediate rectification.
Three, strengthen the dynamic management of safety production license.
In accordance with the spirit of "Regulations on the Administration of Safety Production License of Construction Enterprises", our town has strengthened the dynamic management and inspection of safety production license of construction enterprises and safety production assessment certificate of "three types of personnel": First, strictly control market access and regard safety license as an important examination condition in the project bidding stage; Second, when issuing construction permits, the safety production license and the safety evaluation certificate of three types of personnel are necessary conditions; Third, when safety supervision is put on record, the above two contents should be strictly checked again; Fourth, in the daily supervision of safety production, whether the construction enterprise reduces the conditions of safety production is an important supervision content. Through layers of checks, the province's construction enterprises safety production license and three types of personnel safety production assessment certificate to implement dynamic management.
Four, continue to deepen the special rectification work of safety construction.
In order to implement the spirit of the document "Notice on Organizing Special Renovation of Building Safety" issued by the Ministry of Construction, effectively strengthen the building safety work in our town, effectively curb the frequent falling accidents from high places, and ensure the safety of people's lives and property, the key points of preventing collapse accidents are: foundation pit (trench), earth and stone collapse, scaffolding collapse, high formwork collapse, construction hoisting machinery and fence collapse, and other major accidents that are prone to mass deaths and injuries. The key points to prevent falling accidents from high places are: hanging operation from high places, hole opening, edge operation, installation, maintenance and dismantling of material hoists, construction hoists and lifting machinery, hanging basket operation, erection and dismantling of scaffolding, curtain wall, dry hanging stone work, unloading platform, mobile operating platform and horse's head, etc. At the same time, combining the special safety rectification with daily safety management, through the usual supervision and inspection, the special safety rectification was deepened, a number of hidden dangers of accidents were eliminated, and a long-term supervision mechanism for safety production was gradually formed, which further improved the situation of safety production.
Five, pay close attention to the weak links in production safety.
Our town always adheres to the policy of "safety first, prevention first and comprehensive treatment" and strengthens the supervision of weak links in project safety management such as resettlement sites and construction sites; Strengthen the ability of construction enterprises to control the dangerous sources on the construction site, and establish and improve the emergency rescue plan for major construction accidents; Regularly analyze the situation of production safety, find out potential safety hazards in time, find weak links, strengthen supervision and inspection of accident-prone areas and weak links, pay close attention to accident prevention in advance, and achieve "moving forward". By taking these targeted preventive measures, the occurrence of construction production safety accidents has been curbed.
Summary of the work of the construction unit 5 "Responsibility is more important than Mount Tai" in safety production, and construction safety cannot be ignored. Now let me summarize the construction safety work of our company in the second half of xx.
First, implement the responsibility system for construction safety and improve the safety system.
Company leaders attach great importance to the work of construction safety in production, and regard this work as a major event of stressing politics, ensuring stability and promoting development, and bring it into the target management system. On the one hand, adhere to the "safety first,
Prevention first, comprehensive management "policy, with the implementation of the responsibility system for production safety as the core; On the other hand, focus on construction site supervision and fully implement the implementation of various specifications. It has achieved all-round and multi-angle supervision of the construction work in the whole region.
Second, increase publicity and strengthen safety education for migrant workers.
Most front-line operators come from rural areas, with low education level, weak safety awareness and poor self-protection awareness. Therefore, strengthen workers' safety awareness, improve safety skills and strengthen safety production propaganda.
Communication and education are very important. On the one hand, urge all construction units to implement their responsibilities and put the system on the wall; On the other hand, the safety production education activities will be brought into the normal supervision, so as to ensure that every construction worker receives meticulous and serious fire safety education, comprehensively improve the safety awareness of construction workers, and create a strong atmosphere of "paying attention to safety and caring for life".
Third, strengthen site management to ensure nip in the bud.
1, urge the construction unit to keep the temporary fire lane on the construction site and ensure its smoothness.
2. It is required that the construction site must be equipped with fire fighting equipment, so that the layout is reasonable and the selection is reasonable.
3. Require the construction site to ensure sufficient water resources to meet the water requirements during the fire.
4. Strictly manage the qualification of special operators, requiring the operators of electrical equipment installation and electric and gas welding to have corresponding special operation qualification certificates.
5. Strengthen on-site material management. Safety nets and dense mesh safety nets used in the construction site must conform to national standards or industry standards, and flammable and combustible materials shall not be used.
6. Require the construction unit to establish and improve the management system of temporary electricity consumption, strengthen the construction management of temporary electricity consumption, and strictly implement the specifications for temporary electricity consumption on the construction site.
7. The construction unit is required to strengthen the daily management of temporary dormitories and office buildings, and the management of doors and windows of work sheds and single-person areas should meet the fire control requirements.
Through this series of measures, the construction work in our area is generally in a controllable state, and no safety accidents have occurred.
;