Emergency plan for power failure in computer room
Emergency plan for power failure in computer room

Introduction: Emergency plan refers to emergency management, command and rescue plan in the face of natural disasters, major accidents, environmental hazards, man-made destruction and other emergencies. The following is the emergency plan for power failure in the computer room that I have carefully compiled for you. Welcome to read!

1 emergency plan for power failure of computer room. general rule

1. 1 purpose

In order to better cope with unexpected events such as power failure in computer room, improve the ability to cope with various power failure events, establish and improve a reliable emergency mechanism, and minimize the impact of various power failure events on various departments of the company, with reference to the XXXX Data Center V2. 1 Emergency Handling Process, the XXXX Computer Room Power Failure Emergency Plan (hereinafter referred to as the Plan) is specially formulated.

1.2 working principle

(1) give priority to prevention. Based on safety protection, strengthen early warning and focus on protecting the information and data security of important systems of the company.

(2) rapid response. When an emergency happens, the emergency handling program V2. 1 in XXXX data center can obtain sufficient and accurate information in time and deal with it quickly, so as to minimize the impact of the emergency.

(4) insist? Unified leadership, coordination, clear responsibilities, stick to their posts? The principle of.

1.3 Scope of application

Temporary power failure, sudden power failure and long-term power failure in all computer rooms.

2. Organization and responsibilities

2. 1 organization (contact list and contact information are updated every six months)

Planning operation: main contact person and contact information:

Key IT contacts and contact information

Service desk: extension XXXX. (working around the clock)

Contact persons and contact information of major equipment suppliers:

2.2 Responsibility of each organization

1). The planning and operation department shall notify all departments of the power outage information as soon as possible and take emergency measures. If the diesel generator needs to work, it should check the performance of the diesel engine, whether the output voltage is stable and whether the auxiliary equipment such as diesel oil is sufficient in advance.

2).2)。 IT departments should take emergency measures for power failure in time, notify relevant departments to make important data backup, and notify the equipment suppliers in the computer room, and prepare for power failure at the same time. In order to ensure the normal operation of all equipment in the computer room during the power outage and after the power supply is restored, all relevant IT personnel must be on standby at any time during this period.

3). The equipment supplier of the computer room shall provide technical support for relevant equipment. In case of planned power outage, an emergency plan for power outage should be made in advance. During the period from power outage to power supply restoration, the equipment should be in standby state at any time, and all equipment will return to normal. Technical support personnel for important and key equipment should be on standby at any time. In case of sudden and temporary power failure, remote technical support should be provided as far as possible.

3. Emergency Plan of Information Technology Department

3. 1 Emergency Plan for Long-term Power Failure of Computer Room

(1) After receiving the notice of long-term power outage, you should ask the reason and specific time of power outage, and inform the power outage announcement through the system service desk or telephone in time, requiring all departments to stop business, save data, and turn off all electrical equipment that can be turned off before power outage.

(2) According to the length of power outage, coordinate the planning and operation department to deploy emergency measures, check whether the emergency equipment is normal, and test the performance of emergency equipment by simulating power outage when time permits.

(3) Statistics of the electricity consumption of the equipment in the computer room, and making a power outage plan.

(4) All relevant technical support personnel are deployed in place to ensure the normal operation of important systems and equipment during the power outage, and all systems and equipment will operate normally after the power supply is restored.

(5) Inform relevant departments to strengthen the inspection of equipment and areas with potential safety hazards (such as elevator rooms and water rooms). Ensure the safety of company personnel and property during power failure.

(6) Computer room management personnel should record the causes of the incident and the emergency measures taken during this period in detail, and put them on record.

3.2 Emergency Plan for Sudden Temporary Power Failure in Computer Room

(1) Relevant personnel should immediately report to the department head when they find a sudden power outage, so as to know the reason and time of power outage in time, and immediately check whether the UPS and other equipment in the computer room are operating normally, check whether the systems are operating normally, and at the same time query the relevant records of the equipment in the computer room, calculate the available power supply time of UPS under the current situation, and report to the relevant department heads. Please refer to XXXX Data Center Emergency Handling Process V2. 1 for the specific event operation process.

(2) Notify all business departments of the power outage, judge the duration of the power outage and take corresponding emergency measures, and remind all departments to make data backup just in case.

(3) Notify relevant departments to inspect the operation of equipment (such as elevators, water rooms, etc.) with major security risks to ensure the safety of company personnel and property.

(4) Inform the IT department's computer room management personnel and computer room facilities related personnel to enter the emergency standby state.

(5) After returning to normal, find out the cause of power failure and record it in the computer room safety management log.

4. Training and practice

4. 1 training

The IT operation and maintenance department and the relevant personnel in the computer room should carry out emergency treatment training such as power failure in the computer room at least once a year to improve the emergency treatment ability of the computer room management personnel and their relevant personnel.

4.2 Plan drill

Each emergency organization shall arrange a drill at least once a year to find out the problems existing in the emergency work system and working mechanism, as well as spare equipment and systems, constantly improve the emergency plan and improve the emergency handling capacity.

5. Supplementary provisions

5. 1 plan update

This plan is revised and improved in a timely manner in combination with drills and implementation.

5.2 Responsibility and rewards and punishments

Emergency institutions shall commend and reward the collectives and individuals who have made outstanding contributions in the handling of emergencies; For dereliction of duty, resulting in adverse effects or serious consequences, according to the relevant provisions put forward opinions, and shall be investigated for responsibility according to law.

5.3 Expression and explanation

This scheme is formulated and explained by the IT Operation and Maintenance Department.

5.4 Implementation or Effective Time of the Plan

This plan shall be submitted to the department for discussion and implemented after approval.

;