The construction quality should be based on Code for Construction and Acceptance of Electrical Equipment Installation Engineering (GBJ232-82), Standard for Quality Inspection and Evaluation of Building Electrical Installation Engineering (GB303-88), Code for Construction and Acceptance of Automation Instrument Engineering (GBJ93-86) and Standard for Quality Inspection and Evaluation of Automation Instrument Engineering (GBJ13/4).
Three links and six stages should be grasped in the construction process:
1, tee
Joint review of construction drawings for weak current integrated system: Joint review of drawings is an extremely serious and important technical work. Doing a good job of joint review of drawings seriously plays an important role in reducing errors in construction drawings and ensuring and improving engineering quality. The blue prints.the design shall be organized and led by the general contractor of weak current engineering, with the participation of the construction unit, equipment suppliers of each subsystem and system installation contractor, step by step. According to the nature of the project, drawings, etc. , respectively, to organize joint review work. The results of the joint hearing shall form a summary, which shall be signed by the design, construction and construction parties, and issued separately as a supplementary technical document for the construction drawing.
Duration arrangement of weak current comprehensive system: determining the duration arrangement is the main measure for construction schedule management, personnel organization and ensuring the timely completion of the project.
Technical disclosure of weak current integrated system engineering construction: the main contents include new technology, new technology, new equipment and operation method, new material performance, precautions for embedded parts, etc. Technical disclosure shall be recorded accordingly.
2. Six stages
Coordination between reserved holes, embedded pipes and civil works in weak current integrated system
Coordination between trunking frame construction and civil engineering
Coordination of wiring of weak current integrated system and layout of central monitoring room with civil engineering and decoration engineering.
The sequence of positioning, installation and terminal connection of weak current integrated system equipment is as follows: central monitoring equipment; Field monitor; Alarm probe; Sensor; Camera; Card reader; Computer network facilities
The debugging sequence of weak current integrated system is as follows: central monitoring equipment; Field monitor; Terminal equipment is terminated in different areas; Program demonstration; Partially open; All open. The debugging cycle takes about 30-45 days.
Weak current comprehensive system acceptance (1) system acceptance documents need to provide the following weak current system acceptance documents to the owner: engineering acceptance letter; The system completes the report; System monitoring point setting table; System block diagram; Floor monitoring and information point distribution map; Description of each floor distribution frame; Wiring management and network connection; Description of the termination tag; System Test Report (2) System Training