Chapter I Compilation Basis
1, the design drawing of the storey-adding project of XX teaching building designed by Beijing XX Architectural Engineering Design Co., Ltd.
2. Bidding documents provided by the owner.
3. Investigation on the construction site and surrounding environment.
4. Relevant national construction and acceptance standards for construction and installation projects, quality inspection and evaluation standards for construction and installation projects, Beijing construction site management requirements and relevant laws and regulations.
5.ISO9000 quality management and quality assurance standards.
Chapter II Project Overview
This project is located in Chaoyang District, which is an additional floor of XX teaching building. The original building was a four-story frame structure, but now it has two floors. The fifth floor serves as a dormitory for students and an activity center for veteran cadres, and the sixth floor serves as a lecture hall and a reading room.
Engineering features:
1, the construction area is two floors *** m2, the site area is 950 m2, the first floor area is 906, and the site is small.
2. The height of the five and six floors added is 3.9 meters and 4.3 meters respectively, and the eaves height after adding floors is 24.6 meters.
3. The original building and the newly added two-story structure are cast-in-place frames, the six-story roof adopts steel roof truss horizontally, and the roof adopts profiled steel plates. After adding stories, the seismic fortification intensity of the whole structure is 8 degrees, and the seismic grade of the frame is level 2.
4. The walls are all made of aerated concrete blocks, with the outer wall thickness of 250mm and the inner wall thickness of 150mm.
5. The external decoration and the original external decoration are consistent with the ceramic tile setting.
6. Interior decoration:
(1) Floor: the reading room, activity center, walkways and stairwells are cast-in-place terrazzo floors, the bathroom is floor tiles, and the rest offices and dormitories are fine stone concrete floors.
(2) Ceiling: Gypsum board ceiling shall be coated with scrub-resistant paint, and the bottom of stair floor shall be coated with scrub-resistant paint.
(3) Interior wall surface: scrub resistant coating.
7. Door and window engineering: aluminum alloy windows and wooden doors.
8. Pipeline works: including heating, domestic water supply, drainage and fire fighting.
9. Electrical engineering: including underground laying of steel pipes, threading in pipes, installation of lamps and lanterns, installation of switch sockets, installation of distribution boxes and lightning protection and grounding systems.
Chapter III Construction Deployment
(1) Project objectives:
1, quality objective: excellent.
2. Safe and civilized construction goal: strive for a civilized and safe construction site in Beijing.
3. Construction period: reasonably divide the construction flow section, scientifically arrange the working procedures, and ensure the contract construction period.
4. Management objective: standardize the project management behavior, fully mobilize the positive factors of all members of the project management department, and take advantage of our advantages in construction, operation and technical management to realize modern management. Ensure that the project reaches the first-class level in management, quality, civilization and style, so that users can rest assured and be satisfied.
(2) Organization:
1. organization: organize the project according to the project method and set up the project management department for adding floors to the office building. The construction site is equipped with professional technicians, foremen, safety officers and quality inspectors, who are respectively responsible for technical management, construction management, safety protection and quality inspection. Equipped with rich practical experience and high-level old workers responsible for the main body, decoration quality. The project intends to work on site to solve the problems in the construction process in time.
(1) leading group: composed of project manager, deputy project manager and chief project engineer, responsible for leading, directing, coordinating and making decisions on major issues of the project, and fully responsible for project progress, cost, quality, safety and civilized construction on site.
(2) Technical room: responsible for implementing the project construction organization design, dynamic management in the construction process, perfecting the construction scheme, making technical disclosure in the construction process, organizing technical training, handling engineering changes, compiling engineering technical files, organizing material inspection, test and construction test, checking and supervising process quality, adjusting process design and solving technical problems in construction in time.
(3) Construction room: responsible for organizing the implementation of construction, making production plans, completing engineering statistics, organizing the implementation of site layout, production plans, safe and civilized construction and labor organization arrangements at various construction stages, maintenance and maintenance of construction machinery, and management of various construction factors during construction.