Planning of trams in Shenyang
LineNo. Status Station LineNo. 1 Sujiatun Convention and Exhibition Center 5, which is operating Xinglong Daaolai, Yifeng Plaza, Yinka Road, China Telecom, Song Xin Robot, Baitahe Road, Yuexing International City, Fire Corps, Renaissance Plaza, International Software Park, Song Xinzhihuiyuan, Greentown Quanyun Village, Huamao Center, Operation Center, Shangyingli City, Fucheng Ming Di and International School. Line 5:45-2 1: 15 2 of Xinglong Daaolai is operating Xinglong Daaolai, Yifeng Plaza, Yinka Road, China Telecom, Song Xin Robot, Baitahe Road, Yuexing International City, Fire Corps and so on. Xinglong Daaolai 5:30-2 1:20 Taoxian Airport Line 6:30-22: 103 is operating Century Building, Baitahe Road, Zhonghai Kangcheng, First Guanghe City, China Trade Center, He Hong Plaza, Science and Technology Museum, Lumei College, Jinlian Industrial Park and University Science and Technology City. Century Building 6:30-20:30 University Science and Technology City Line 6:00-20:005 is operating the Olympic Sports Center, Shenyang Customs, Jinshui Flower City, Olympic Sports Swimming Pool, Administrative Service Center, Hunnan Library, Army General Hospital, Hunnan Experimental School, Vanke New Mile, Jianzhu University, Jindi Binhe International, Comprehensive Bonded Zone, Vanke New City, Donghu School, Warm Harbor, etc. Navigation Building, Guanbo, Shanghai Expo Hall and Shenfu New City Olympic Sports Center are under construction at 6: 00-2115. Shenfu New City Line is under construction at 5:30-20:006, that is, Citizen Square East, Academy of Fine Arts, Tennis Center, Mozishan Sports Park, Hangtian Road West and Qianjinhui Hotel 20/kloc-

Original plan: to build 5 lines with a planned total length of 65km and 54 stations with an average spacing of1.2km. ..

The final plan is to integrate five lines into four lines with a total length of 60 kilometers and 73 stations, with an average of 820 meters.

The estimated investment of the modern tram project is 4.86 billion yuan, and the depot 1 block (including the control center) is located in Hunnan New Town. Two comprehensive transportation hubs, located in the Olympic Sports Center and 2 1 Century Building, with 1 parking lot, are located in Shenfu New Town.

On 201February 17, Shenyang Modern Rail Transit turned a new page, and the modern tram project in Hunnan New District officially started.

Wang Min, Secretary of the Provincial Party Committee and Director of the Standing Committee of the Provincial People's Congress, Xu Weiguo, Standing Committee of the Provincial Party Committee and Executive Vice Governor, Ceng Wei, Secretary of the Standing Committee of the Provincial Party Committee and Shenyang Municipal Party Committee, Cui Dianguo, Chairman of CNR, Mayor Chen Haibo and Zhao Changyi, Director of the Standing Committee of the Municipal People's Congress attended the ceremony, and * * * started the start button.

Xi Guohua, President of CNR Group, delivered a speech at the groundbreaking ceremony as the contractor representative of Hunan Hyundai Tram Project. Yang Yazhou, member of the Standing Committee of the Municipal Party Committee, deputy mayor and secretary of Hunnan New District Party Committee, presided over the ceremony.

20 13 In June, the rail transit that disappeared in Shenyang for nearly 40 years will return to citizens' life. By then, the four routes will pass through Taoxian Airport, Quanyun Village, Olympic Sports Center, Shenfu New City and other important nodes, and people in Shencheng will have a variety of new choices, adding a flowing landscape to Hunnan. Among the four modern tram projects, Line 5 has the longest line, which is 2 1.4km, and the other three lines are all less than 15km, among which Line 3 is the shortest, which is 1 1.3km.

The design speed of modern tram in Hunnan is 70km/h, and it is 23km/h in normal operation. It can be calculated that it will only take 39 minutes by tram from the Olympic Sports Center to the airport in the future.

The first phase of Hunnan tram project consists of four lines with a total length of about 60 kilometers. Hunnan New Town has a 1 depot, and Shenfu New Town has a 1 parking lot. There are two comprehensive transportation hubs, which are located in the Olympic Sports Center and 2 1 Century Building. There are 96 stations on the whole line, of which 3 1 station is reserved. Upon completion, Sujiatun Shenyang International Convention and Exhibition Center, Shenyang New South Station, National Games Center, Taoxian Airport, Olympic Sports Center and Shenfu New City will be integrated, and will be seamlessly connected with subway and bus lines through the Olympic Sports Center, 265438+ Century Plaza and other comprehensive transportation hubs.

After the tram is opened, it will be more convenient and faster for citizens to go to the airport. Citizens can get off at the Olympic Sports Center Station by car or subway, and then transfer to the tram for the airport. Total length of the line from the Olympic Sports Center to the airport14.8km.. According to the speed of 23 kilometers per hour, it only takes 39 minutes from the Olympic Sports Center to Taoxian Airport. In addition, trams have an obvious advantage over driving, that is, there will be no traffic jams and time is guaranteed.

It can be calculated that in the future, it takes only 30 minutes to take the tram from 2 1 century building to the National University Science and Technology City, and only 55 minutes from Hunnan No.3 Road to Shenfu New City.

Hunnan modern tram has planned lines 4, 6, 7, 8 and 9, with a total length of about 139 km. After the line is completed, it will basically cover every corner of Hunnan New District. Track laying has been completed in the Innovation section of Line 6, which is about 3.3 kilometers long from Shenzhong Street to Shenben Avenue. Line 6 connects tram lines 2 and 3, Taoxian Airport, Olympic Sports Center and Shenfu New City, and it is expected to be connected to the grid at 20 14.

In 20 14, the construction of Line 4 connecting 1 and Line 3 will also start. Its connecting line from Shen Ying Street to 2 1 Century Building is about 7.8 kilometers long. Four lines connect the Convention and Exhibition Center, Taoxian Airport, New High-speed Railway South Station, Quanyun Village, National Games Operation Center, Olympic Sports Center, New District Administration Center and Shenfu New City. And through the Olympic Sports Center, 265438+ Century Plaza and other comprehensive transportation hubs, it is seamlessly connected with subway and bus lines to realize fast and smooth traffic transfer.

After the formal operation of modern trams, citizens have another choice to go to Taoxian Airport. After getting off at the Olympic Sports Center Station of Metro Line 2, you can take the tram of Line 2 and go directly to the T3 terminal of the airport. Modern tram is an operation mode between subway and bus, which has irreplaceable advantages. Trams have a design speed of 80km/h, a running speed of 30km/h to 40km/h, and each train carries about 300 passengers. Because of the AC drive and computer-controlled braking technology, it runs on a stable track, and there will be no sharp turn or sudden braking like a bus. The stability and comfort are equivalent to those of the subway, but the cost is only one-fifth of that of the subway.

Modern trams use wide doors and windows, and passengers can see the scenery outside the window in the car. Like the subway, the carriage is also equipped with air conditioning, which is warm in winter and cool in summer. The vehicle selection scheme of modern tram operation has been announced in Shencheng Media.

The first batch of modern trams are 28.8 meters long, 2.2 meters high and 2.65 meters wide, which is even longer than the longest bus "Big Mac" in Shenyang at present 10.8 meters. The bodies of these trams are blue, and there are white cranes on the bodies. It is understood that this series of vehicles is an artistic scheme created by the German company Staubach. The car body of a group of trams is divided into three sections with six doors on both sides. Passengers can get on from the front and rear doors and get off from the middle two doors. Coin boxes and credit card machines are installed next to the boarding gate, that is to say, passengers can pay in cash or swipe their cards when they take the tram in the future.