Baiyun Campus will be built in three phases. The first-phase construction projects are as follows:
1. Main construction projects: teaching building (about 65438+6500m2), library (about 30000m2), school administration building (about 14200m2), teaching administration building of secondary college (department) (about19/kloc-0) Student apartment (about 60,000m2), campus gate and transparent fence, 400M plastic runway, 1 standard track and field (football) stadium, 10 outdoor basketball and volleyball court.
2. Supporting infrastructure of the first-phase construction project: the construction site is excavated and leveled; Part of the main outdoor greening and environmental landscape; Main roads; Some outdoor motor vehicle parking lots and non-motor vehicle parking lots; Main power supply and distribution facilities; Main water supply and drainage facilities; Water supply and drainage underground pipe network; Fire underground pipe network; Power supply underground pipe network; Network, telecommunications, security and other weak current systems always control the main facilities and underground pipe network.