Foundation pit support contract (1)

Party A: Shaanxi Eleventh Construction Engineering Company of Shaanxi Construction Engineering Group (hereinafter referred to as Party A)

Party B: Northwest Nonferrous Engineering Co., Ltd. (hereinafter referred to as Party B)

Through negotiation between both parties, Party A entrusts Party B with the task of supporting the foundation pit of the Library of Hangyuan. In order to promote the smooth progress of the project, the following agreement is reached:

(1) Project Location: No.259, West Second Ring Road, Hangyuan, Tuanjie Middle Road, Xi City.

(2) Project Name: Foundation Pit Support of Aviation College Library.

(3) Project content: slope repairing, hole forming, grouting, cage making, netting and concrete spraying.

(4) Contracting method: contracting for work and materials.

(5) Project cost: 140 yuan/㎡. (The quantity of works shall be settled according to the design scheme and changed according to the actual area. )

(VI) Payment method: 50,000 yuan will be paid for the foundation pit support, 50% of the total cost will be paid for the third floor of the main project, and all the remaining project funds will be paid for the foundation pit support after the main project is capped.

(7)3.5 1% tax shall be withheld by party a. ..

(VIII) Everything entrusted by Party A to Party B's construction personnel shall be calculated by the hour, and all work stoppages caused by the lack of material supply for projects not contracted by the contractor shall be calculated by the hour.

(9) When machinery is used in the back office, Party B's shift fee shall be extracted according to the provincial construction quota.

(X) Party B must abide by all rules and regulations when entering Party A's unit, and the labor protection articles shall be solved by Party B itself.

(1 1) Quality acceptance standard: according to the actual situation, the construction acceptance shall be carried out according to the current national construction acceptance standard (Party B shall provide all engineering data for technical data).

(12) During the construction period, due to the heavy workload of Party A, Party A shall provide accommodation ... During the construction period, Party B shall be responsible for any industrial accidents.

(13) During the construction period, Party A shall closely cooperate with Party B to do a good job in civilized construction, and Party B shall strive to complete the engineering tasks with high speed and high quality.

(14) Project duration: Party B shall complete the project within 10 days after the earth excavation, counting from the date of mobilization. In case of rain or other force majeure accidents, it can be postponed.

(15) this agreement shall come into effect after being signed by both parties, and shall automatically become invalid after the acceptance and settlement are completed.

(XVI) This Agreement is made in quadruplicate, with each party holding two copies.

Party A: Shaanxi 11th Construction Engineering Company of Shaanxi Construction Engineering Group? Party B: Northwest Nonferrous Engineering Co., Ltd.

Employer (seal):? Construction unit (seal):

Person in charge: (Gao Yanming) Person in charge:

Contractor: (Korea) Contractor: (Hu Yanhong)

On-site representative: (Cheng Yue)? On-site representative: (Wu? Jump)

Electricity? Words: * * * * * * * *? Electricity? Words: * * * * * *

Bank of deposit:? Bank of deposit:

Account? Number: account number? Number:

Signed on * * * of * *.

Foundation pit support contract (II)

Party A (Employer):

Party B (contractor):

Through negotiation between Party A and Party B, the foundation pit support of 9# building and 10# building of Lan Xin Garden in Haikou City is contracted to Party B in the form of all-inclusive construction, and Party B shall undertake the construction. In order to clarify the specific conditions of the project and the responsibilities of both parties, this agreement is signed on the basis of equality, voluntariness and fairness.

I. Project Content and Contracting Method

1. Project content: foundation pit support, anchor rod, anchor shotcrete with hanging net, channel steel waist beam.

2, according to the drawings, combined with the actual project settlement.

3. Contracting methods: contracting machinery, contracting labor, contracting materials, contracting taxes and fees, contracting management fees, contracting water and electricity, contracting safety, contracting duration and contracting quality.

Second, the construction period, safety and civilized construction

1, construction period

(1) Party B completely obeys Party A's construction progress requirements and ensures completion, and can increase the labor force at any time as needed, otherwise all economic responsibilities arising therefrom shall be borne by Party B. ..

(2) If Party B obviously delays the progress, Party A may contract part of Party B's original work to others according to the situation.

(3) If the progress is seriously delayed or stopped due to Party B's reasons, Party A has the right to withdraw Party B, and the corresponding losses shall be borne by Party B. ..

2. Security:

(1) Abide by all safety rules and regulations of Party A and the Project Department, strictly implement Party A's safety operation specifications and safety technical disclosure, and ensure safety requirements.

(2) Use all kinds of machinery and small electric tools correctly, and it is forbidden to operate illegally; All kinds of machinery and small electric tools must meet the requirements of Party A. ..

(3) Special types of work must have a valid special operation certificate.

3, civilized construction

(1) is responsible for all civilized construction and sanitary cleaning of its own construction and living quarters.

(2) Ensure that the site is cleared after work every day.

Third, the responsibilities of both parties.

Party A's responsibilities:

1, fully responsible for site construction management, technical guidance and safety technical disclosure, and organize three-level education.

2. Designate a person to be responsible for the construction of subdivisional work, issue the construction plan, and manage the work arrangement, inspection, supervision, rectification, acceptance, safe production, civilized construction and project progress.

3. Support and participate in team building and overall management, organize, coordinate and solve problems and relationships in work.

4. Party A shall provide Party B with water and electricity connection points. ..

Party B's responsibilities:

1. After check-in, provide Party A with a copy of the ID card of the floating population and family planning registration.

2. Seriously accept the tertiary education organized by Party A and participate in daily safety training and education before taking up the post.

4, without the permission of the project department, it is forbidden to bring family members and children into the construction site and living quarters.

4. Party B must abide by various management systems and reward and punishment measures of the Project Department.

5. Pay the water and electricity expenses of Party A according to the actual consumption.

Four. Project price (including tax)

1, channel steel waist beam per square? 202.24? Yuan.

2, steel flower tube per meter? 92? Yuan.

3, hanging net spray anchor per square meter? 130? Yuan.

Verb (abbreviation of verb) settlement method

According to the actual site to complete the calculation of engineering quantity.

Settlement and payment methods of intransitive verbs

Through negotiation between Party A and Party B, during the construction process, Party A will not prepay Party B's entrance fee and progress payment, and pay the balance of the project payment after the project is completed and accepted by Party A..

Seven. others

1. Matters not covered in this contract shall be discussed separately by both parties.

2. This contract shall come into effect after being signed by both parties, and shall have the legal effect of the contract, and shall automatically become invalid after the payment for goods is made.

3. This contract is made in duplicate, with each party holding one copy.

Party A: (Seal) Party B: (Seal)

Hainan yunshun real estate development co., ltd

Address: 4th floor, Building D 14, Dalong Garden, Haida Road, Haikou? Domicile:

Representative of Party A: Representative of Party B:

Bank of deposit: China Bank Haikou Qiongshan Sub-branch? Bank of deposit:

Bank account number: Bank account number:

Tel: Tel:

Fax:? Chuan Zhen:

Postal code:

date month year

Foundation pit support contract (3)

Employer (Party A):

Contractor (Party B): Beijing Jiahengli Construction Engineering Co., Ltd.

Project name: foundation pit support project of a building in a center phase II.

Project location: Fangsheng Town, Bazhou City.

In accordance with the Economic Contract Law of the People's Republic of China, the Regulations on the Contract of Construction and Installation Projects and other relevant regulations, in order to clarify the responsibilities, rights and obligations of both parties, Party A and Party B have reached the following agreement on the project contracting through friendly negotiation:

Article 1 Contract Method, Contract Scope and Project Cost

1. 1 Contract method: contracting for labor and materials.

1.2 contract scope and project content: foundation pit supporting project of a building in the second phase of a center.

1.3 total contract price:? 2245 10.4 yuan, in words: two hundred and twenty-four thousand Wu Bai four yuan (note: engineering quantity:1247.28m2, unit price: 180 yuan/m2).

Among them, the total contract price is fixed, including all costs in the construction process, but excluding general contracting service fees, utilities and taxes.

Rule number two Time limit for a project and commencement and completion date

2. 1 The time limit for slope protection of soil nailing wall in this project is tentatively set as 12 days. In case of special circumstances, the above construction period shall be adjusted accordingly, and in case of force majeure, the construction period shall be postponed accordingly.

Rule three. construction quality

3. 1 Engineering quality requirements: qualified.

Article 4? On-site representatives of both parties

4. 1 Name of Party A's field representative:

4.2 Name of Party B's field representative: * *

4.3 When Party B's on-site representative changes, it shall notify the other party in writing three days in advance, and clearly point out the handover time and authority.

Article 5? Party A's responsibilities

5. 1 Before the commencement of construction, Party A shall provide Party B with hydrogeological data, detailed engineering geological data related to construction such as underground pipe network and underground structures, as well as construction drawings and technical requirements.

5.2 Be responsible for removing the above-ground and underground obstacles (including underground cables, wires and pipeline facilities) before construction. If it cannot be dismantled for some reason, it is necessary to put forward specific treatment opinions and protective measures, and make a written disclosure to Party B at the scene.

5.3 Provide access between the construction site and public roads, meet the requirements of construction and transportation, and make the construction site leveling.

5.4 Before starting work, solve the problem of disturbing people by on-site construction involving city appearance, sanitation and night construction, and ensure that the project starts on time and the construction proceeds normally.

5.5 Assist Party B to handle relevant certificates required for construction, and provide Party B with free accommodation.

5.6 The representative of Party A has the right to supervise and inspect the quality and progress of Party B's project, and assist in solving the problems arising in the construction and the contradictions among various units. After Party B's self-inspection is qualified, Party A will organize inspection and go through the acceptance procedures to coordinate the relationship between earthwork excavation and slope support. Earthwork must cooperate with slope support construction, and carry out earthwork excavation according to the requirements of slope support on the premise of ensuring the safety of slope support.

5.7 Issue necessary instructions, confirmation and approval in time, and provide construction cooperation and payment according to this contract.

5.8 Party A shall ensure the dewatering effect, and the construction site can meet the construction requirements of Party B after dewatering. Party A shall be responsible for the slope safety problems caused by unfavorable precipitation, which has nothing to do with Party B. All losses caused by the settlement of surrounding buildings caused by precipitation shall be borne by Party A, and Party B shall not bear any responsibility.

Article 6? Party B's responsibilities

6. 1 Strictly abide by national quality, technology and safety regulations and Party A's on-site rules and regulations.

6.2 According to the time limit for a project and the conditions of the construction site, prepare the feasible construction technical scheme, construction organization design and progress plan, and submit them to Party A for approval; Carry out the construction in strict accordance with the approved construction organization design, ensure that enough construction machinery and personnel are invested, accept the supervision and inspection of Party A at any time, and correct the deviation as required.

6.3 Party B shall take full responsibility for the safety and rationality of the technical scheme of this project and the implementation results of this project. Party B shall ensure the slope safety from the start of the project to the completion of the foundation earthwork backfilling project.

6.4 Ensure safety in production, be responsible for handling accidents caused by our responsibility and bear corresponding expenses.

6.5 Party B shall strictly obey the management of Party A and strictly implement Party A's rules, instructions and instructions, including submitting various reports, plans, schemes, measures, records, lists, certificates and other documents or materials at the time, format and content required by Party A, and attending the meetings convened by Party A. ..

6.6 If Party B encounters unforeseeable or insurmountable difficulties in the construction process, it shall report to Party A in time.

Article 7? acceptance of works

7. 1 party a shall check and accept the project completion results and project quality according to the relevant design data, the actual situation of the completed project on site and the current relevant national codes and standards.

7.2 After the quantity and quality of the completed project meet the requirements and the contents agreed in this contract, both parties can handle the relevant project acceptance and completion procedures.

Article 8 Payment of project funds

8. 1 Payment of project funds: After signing the contract, Party A shall pay 30% of the total contract price in advance to Party B, 70% of the total contract price before leaving the site after the slope protection project is completed, and the balance shall be settled within one week after the earthwork backfilling. (When Party A pays Party B the project payment, Party B shall provide Party A with the corresponding material invoice)

Article 9? debate

9. 1 If there is any dispute between Party A and Party B, it shall be settled through friendly cooperation. If negotiation fails, both parties may bring a lawsuit to Bazhou People's Court where the project is located.

Article 10? breach a contact

10. 1 If Party A fails to give clear instructions, confirmation and approval in time, fails to perform all its obligations as agreed in the contract, and takes other actions that make the contract impossible to perform, it shall be liable for breach of contract, and the construction period shall be postponed accordingly.

10.2 As Party B fails to complete the project according to the contract time limit, the construction quality fails to meet the specifications and contract requirements, and Party B fails to fully perform all its responsibilities and obligations, Party B shall pay 0.3‰ of the total project cost as agreed in the agreement as penalty per day.

10.3 Unless both parties agree to terminate the contract, or the contract cannot be performed due to one party's breach of contract, the breaching party shall still perform the contract after assuming the above liabilities for breach of contract.

10.4 if the contract cannot be performed due to one party's breach of contract, the other party shall notify the breaching party to dissolve or terminate the contract three days in advance, and the breaching party shall bear the liability for breach of contract.

Article 11? Treaty wording

1 1. 1 This contract shall come into force as of the date of conclusion.

1 1.2 After the earthwork backfilling project is completed, Party B will fully perform all its responsibilities and obligations, and this contract will be terminated after Party B receives the final payment for the project completion settlement.

This contract is made in two originals, one for each party; This contract is made in duplicate, one for each party.

1 1.4 applicable law of the contract: relevant laws, regulations and normative documents of People's Republic of China (PRC).

1 1.5 Standards and specifications applicable to this contract: it shall be implemented according to the current national quality evaluation standards and construction technology acceptance specifications.

Article 12? supplementary terms

12. 1 Party B's civilized construction on site shall be under the unified management of Party A and meet Party A's requirements.

12.2 Party B shall cooperate with other contractors of Party A according to Party A's requirements during the construction process, and shall not hinder or obstruct the work of the other party or destroy the work results of the other party without Party A's permission under any circumstances, otherwise it shall bear corresponding responsibilities.

12.3 matters not covered in this contract shall be agreed by both parties through consultation.

(There is no text here)

Party A: Party B: Beijing Jiahengli Building

Engineering co., ltd.

Legal representative:

Handler: Handler:

Address: Yifa Industrial Park, Huangcun Town, Daxing District, Beijing 14

Date of signature: year month day? sun