In normal study, work and life, meeting minutes are increasingly needed to handle affairs, and meeting minutes are generally written in the third person. How should we draft the meeting minutes? The following is a model essay on the minutes of the meeting of construction enterprises compiled by me for your reference, hoping to help friends in need.
Minutes of meeting of construction enterprises1:April 18 pm, xxx.
Venue: Conference Room of Xiruo Middle School in Dali County
Participants:
Moderator: Zhang xx
Meeting contents:
First of all, Zhang xx clarified the meeting discipline. In the future, everyone will be fined 10 for being late, and 50 for being absent or asking for leave without reason.
Later, Zhang xx explained that due to the recent rainy weather, the water content of concrete was high, and the formwork reinforcement and support were not in place, which led to the overall sinking of the slab and beam in the northern section of the first floor of No.2 dormitory building. In this regard, on the morning of April 17, 2007, President Shen held a special meeting with the following contents:
1 The northern section of No.2 dormitory was shut down for three days, and local formwork was removed for observation on April 20th.
2. Observe the results, form written materials and report them to the company, Education Bureau and Li Sen Labor Service Company.
3. Give corrective measures.
Zhang xx, the production manager of the project department, summarized and expounded the reasons for the sinking of the north section on the first floor of No.2 dormitory building:
1. There has been no quality accident in the project department since the project started, and the problems in the north section of the first floor of No.2 dormitory building belong to poor quality management, and the leaders have unshirkable responsibility for this.
2. There are some problems in project management, and the quality management is lax.
3. Team leaders and workers have a weak sense of quality and are unaware of the seriousness of the problem.
4, and then the project department according to the actual situation to develop punishment measures, and report.
5. In the future, the foreman's sense of responsibility must be in place, and Lisen Labor Service Company will fully cooperate with the foreman's project management. If it doesn't obey, it would rather stop working.
Koryo, a supervision company, said: On April 17, 2007, the quality accident of No.2 dormitory building was caused by the untimely reinforcement. If it collapses, it will cause serious quality and safety accidents. There are several reasons for this development. The impact cannot be estimated now, but it will be known in three days. I hope this quality accident has little impact. Everyone should consider how to do a good job in rainy season construction in the future.
The supervisor put forward several requirements for future construction:
1, the backfill quality must meet the standards;
2, management institutions should be strengthened, so that the upload issued, there are problems in a timely manner, bad reports in a timely manner;
3. In view of the quality accident of No.2 dormitory building, we should insist on quality in the future.
Secretary for Education Xie Zhenguo speaks:
1, supervisors and project department personnel should pay enough attention to it, and do a good job in the future to prevent similar things from happening again. In the future, we must catch up with the progress on the premise of ensuring quality.
2, the project department should do a good job in the rainy season construction plan and implementation;
3. Next Monday, report the treatment scheme and measures to the supervision unit.
Manager Zhang continued to sum up last week's work. The summary is as follows:
1. Last Tuesday, deputies from provincial, city and county people's congresses inspected this project;
2. The drawings of the east teaching building and experimental building of the school were changed according to the actual situation;
3. Progress: The construction of the second floor of the office building, the completion of the first floor of the No.2 dormitory building, the foundation construction of the No.1 dormitory building, the piling of the dining room, the piling of the gymnasium and the wall laying of the East teaching building are basically completed.
Problems in construction last week:
1, the shortage of steel workers has affected the construction progress of the office building;
2, improve the quality consciousness, do civilized construction, clear after work;
3, during the period of construction, close cooperation between each type of work;
Next, it is required to send odd jobs to clean up the silt on the main roads of dormitory buildings and office buildings.
According to the construction area of No.2 dormitory building and office building, there shall be no less than 50 rebar workers and no less than 20 rebar workers in 1 dormitory building.
Work plan for next week:
1, west teaching building, library hoist installed in place;
2. Except waterproof, the masonry of the East Teaching Building and the Experimental Building is basically completed, and the roof is over;
3. The end of the foundation wall of the West Teaching Building;
4. Indoor trench bottom and secondary backfill in the east area;
The third floor of the south section of No.5.2 dormitory building has ended, and the steel bars will be bound in the north section on the 20th. 、
6. After the foundation of1dormitory building is completed, carry out indoor backfilling;
7. The end of the second floor of the office building;
8. Piling in the gymnasium;
9. Start the in-situ testing work before the reception of the main experience in the East Fourth Floor, and the reference room will do the in-situ testing for approval.
Announce progress node target:
1, the east teaching building and experimental building were accepted in early May, indoor and outdoor painting was carried out in mid-May, and exterior wall tiles were constructed at the end of June;
2. The main body of the west teaching building and library was accepted in early June, indoor and outdoor painting was carried out in mid-June, and external wall tile construction was carried out at the end of July;
3. The office building and dormitory building No.2 will be capped at the end of June, the infilled wall will be constructed at the beginning of June, and the main body will be accepted at the end of July. Indoor and outdoor painting began in early August, and exterior wall tile construction began in early September.
4. The dormitory building 1 was capped at the beginning of July, the infilled wall construction was carried out in the middle of June, and the main body acceptance was carried out in the beginning of August. Indoor and outdoor painting will be carried out in mid-August, and external wall tile construction will be carried out in late September.
From the end of May to the end of June, Weinan conducted an unannounced visit to check the quality and safety. All departments should do a good job in response inspection.
The weather is bad and rainy recently, so the construction progress can't be delayed. It is emphasized that water and electricity should be installed and embedded in one day. And report the arrangement list of hydropower installation personnel to the production manager.
The open trench outside the scaffold will be excavated at the construction site, and the work of creating a civilized construction site will be arranged separately.
Deng Quality Inspection Speech:
1, single support is not allowed for formwork support, and the pad should be processed.
2, the secondary masonry quality is poor, mortar joint is not full;
Manager Zhang asked the labor service company to sort out the changes in the drawings into written materials and report them. Emphasize that the second floor of the office building will be capped on April 30. If it can't be capped, it will be fined 5000 yuan. At the end of April, the infilled wall in the East District was completely completed, except for the changed part, otherwise, a fine of 654.38+00,000 yuan was imposed.
Minutes of Meeting of Construction Enterprises 2 Name of Meeting:
Meeting time:
Sign-in column: the meeting sign-in table is attached.
Construction unit: X County X Management Committee Central School
Supervision unit: X Construction Project Management Co., Ltd.
Construction unit: X Construction and Installation Co., Ltd.
Summary of meeting contents:
Check the implementation of the agreed items at the last regular meeting and analyze the reasons for the unfinished items;
Progress: According to the construction progress plan, the actual progress is relatively lagging behind. Cause analysis:
(1) Manual digging pile is technically difficult;
② Six or seven rainy days;
(3) It is difficult to rent scaffolding steel pipes, and they are not put into use in time, which affects the construction progress.
Safety: there is a phenomenon that workers enter the construction site without taking safety risks. Cause analysis:
(1) Hot weather:
(2) The site management personnel are lax.
Check and analyze the completion of the project progress, and put forward the next stage progress, quality and safety objectives and their implementation measures:
1. The person in charge of the construction site introduces the development of the construction site: At present, the reinforced concrete construction of the second floor beam slab is under way, and the actual progress is slow, and the project quality and construction safety are under control; Put forward some specific progress plans:
1, August 19 Complete external scaffolding and hanging safety net.
2. Complete the three-layer main structure before August 28th.
3. After the meeting, hold a meeting of project department managers and team leaders, formulate measures to catch up with the work, and deploy the next stage of work to ensure that the delayed construction period can be caught up.
Second, the site supervisor put forward the problems existing in the site inspection during the construction process, and the director put forward some specific requirements for the construction unit:
(1) Problems:
1, scaffolding settings do not meet the specification requirements;
2. Whether there are safety helmets and safety ropes;
3. The construction site lacks safety warning signs and operation procedures of construction machinery;
4. No special person opens the gantry crane;
5, the site materials piled up in confusion.
(2), some specific requirements for the construction site:
1, the project department should strengthen the safety inspection of the construction site, and the scaffolding can only be used after special acceptance. Personnel entering the construction site should take safety measures, and safety ropes should be used for aerial work;
2. Set safety warning signs and operating procedures for all on-site hazard sources and special equipment workplaces;
3. On-site electricians, welders, scaffolders and special equipment operators should hold relevant certificates;
4. Continue to increase investment in safety, avoid high-temperature weather operations, and take measures for high-temperature heatstroke prevention;
5. On the premise of ensuring the engineering quality and construction safety, make detailed drawing plans and make plans to catch up with work;
6, the construction site materials should be neatly stacked, building industry information should be timely.
3. Director Liu of the safety supervision station of Zipengshan Management Committee, the construction unit, put forward some opinions on the project safety, and the director of the Education Office and President Wang of the Central School summarized and put forward some specific requirements:
(a), safety supervision station Liu webmaster:
1, the temporary electricity consumption on the construction site should be standardized, and it is not allowed to be overhead anywhere;
2, high temperature weather construction to avoid high temperature time and do a good job of heatstroke prevention and cooling;
3. The project department shall promptly organize rectification and treatment of the hidden dangers found in the inspection.
(2) President Wang of Central School:
1, strengthening safety management is the first;
2. Speed up the construction and ensure the delivery on June 10+00;
3, synchronous staggered construction is the key, completes the construction scheme, and please sign the supervision unit;
4, building, decoration and ancillary materials quality should be guaranteed;
5, data construction should be in place, to achieve data and website synchronization.
Check and verify the payment of engineering quantities and project funds: implement construction funds as soon as possible according to the contract; Solve related problems that need coordination; Other related matters: At the end of August, the supervision unit organized the construction unit and the construction unit to conduct a safety inspection.
Minutes of Meeting of Construction Enterprises On April 29th, 3 xxx, a regular meeting on construction safety was held in the company meeting room. The meeting was presided over by Deputy General Manager Song Hao, and General Manager Duan Gang attended the meeting and made a speech. Responsible persons of various construction sites, key personnel of the company and key personnel attended the meeting. The main contents of this meeting are:
A, the construction site progress changes. As the weather gets hotter, the company works for workers.
People have increased their lunch break, and each construction site can reasonably adjust the workers' work and rest time according to the timetable issued by the company and the actual situation of the construction site.
Second, safety, engineering quality and progress.
( 1)
1. The main problem related to safety is the distribution box. The company requires the distribution box, mixer, wooden shed and other facilities to be rain-proof and smash-proof according to the relevant regulations of the industry to ensure "secondary distribution and tertiary protection". Starting from tomorrow, the company's electricians will inspect the electric shock protectors at various construction sites to ensure the quality and safe use of the electric shock protectors. In addition, the person in charge of each construction site will also check the electric shock protector from time to time to find and solve problems in time to ensure the safety of electricity use.
2, scaffolding and safety nets and other construction facilities over the construction height, must ensure the construction safety.
3. The scraps, nails and other items on the construction site should be cleaned in time, and it is strictly forbidden to throw or misplace them to prevent accidents. In addition, the leftover materials can be used as much as possible, and waste is prohibited. The person in charge of each construction site should strengthen on-site management.
4. When repairing the tower crane, the repairman must wear a seat belt to prevent accidents.
5. The on-site staff must wear safety helmets. If they don't, the person in charge of each site will be fined.
(2) The quality problem is mainly the displacement of constructional column, and each type of work is wrangling with each other. In the next step, the company hopes that each construction site will use the process handover system as much as possible, and the responsibility will go to the process to prevent the phenomenon of wrangling and improve the project quality. The person in charge of the construction site strengthens the project quality management through the pre-shift meeting and daily management.
(3) the progress of the project. The company requires all construction sites to pay close attention to the construction period and speed up the progress according to the contract requirements on the basis of ensuring the quality of the project, so as to ensure that the project is completed on time. This problem is mainly prominent in the Ming Road Garden. I hope that the person in charge of the construction site can pay attention to it and solve it quickly.
Fourth, materials. The person in charge of the site shall report the missing materials to the company as soon as possible. It is forbidden for contractors at each site to directly ask for materials from the company, and the materials can only be entered after being signed by the person in charge of the site and the materials engineer. In addition, each construction site should adjust the materials used by each other as much as possible, and the materials temporarily unused on the construction site can be transported to other urgently needed construction sites for use first, so as to minimize the company's unnecessary expenses on materials and reduce waste. Unused materials shall be transported back to the company in time for unified storage and disposal by the company.
5. Equipment. The company allocates equipment in a unified way to increase the utilization efficiency of equipment, and the damaged equipment should be transported back to the company for maintenance in time. The company will try its best to ensure that each site can replace the damaged equipment in time and reduce the possibility of wasting the construction period. In addition, the unused equipment in each construction site should be transported back to the company in time so that the company can maintain it in time.
Five, the company devolves power to the person in charge of each site, and the person in charge of the site will really make good use of his power. For the foreman and personnel who do not listen to the command and leadership, the penalty will be imposed, and special attention should be paid to the project quality, project progress, site management and other issues, so as to prevent the anticlimactic project and effectively manage the site.
Six, from now on, the company from the long mountain site, establish a safe and civilized construction site, the company requires the site from scaffolding, all in accordance with the standards of safe and civilized construction site construction, the long mountain site into a model project. Next, the company requires large and small projects to be built according to the requirements of Changshan site. By building a safe and civilized construction site, the company's popularity and credibility and its influence in society will be improved. Moreover, the company strives to set up a group company from the second half of this year to next year, and the company will be promoted to the second-class qualification next year. I hope everyone will change their ideas as soon as possible, study hard, improve their management level, and strive to make the company bigger and stronger.
Participants:
Record arrangement:
Minutes of Meeting of Construction Enterprises On the morning of xx, xx, 4 x years, Mr. Xu presided over the meeting of all employees and the meeting of bid manager in the company meeting room. At the staff meeting of the company, Mr. Xu summarized the preliminary work and criticized the technical department for its poor guidance and lax inspection, and the engineering department for failing to report the incoming and outgoing routes in time. At the meeting, General Manager Xu and General Manager Cui made detailed arrangements for the next work priorities of each department and office and each bid section of the company. The main contents of the meeting are summarized as follows:
First, criticize the problems existing in the technical department and the engineering department.
1, the company has repeatedly emphasized and focused on the collation of data of each bid section, but the technical department failed to implement this work due to inadequate measures and guidance.
2. The engineering department and the technical department did not keep their feet on the ground when inspecting the construction site, but they did not understand the drawings thoroughly and failed to find the problems in time: ① the inspection wells in each bid section were not constructed according to the drawings and failed to find them in time; (2) There are potential safety hazards in the retaining wall of Bid 3, and the protective measures were not found and guided in advance, which led to the collapse of the retaining wall, the breakage of telephone poles, and the interruption of water supply and power supply for residents. Delaying the construction period and causing property losses. The engineering department and technical department are required to fully draw lessons from accidents, find potential safety hazards in advance, and take safety protection measures in advance according to the scheme given by the design department.
3. The engineering department failed to report the route, time and license plate number of materials in and out of each bid in time according to the requirements of the headquarters, and the headquarters gave informed criticism. In view of the tight construction period and heavy tasks, and at the same time catching up with the critical period of innovation and health, the engineering department is required to strictly urge all blocks to fulfill the declaration procedures in advance for incoming and outgoing materials, and clean up in time in case of overflow and leakage, and offenders will be prosecuted.
Two, require all departments to focus on the following work
1, the engineering department is given priority to, and the office assists in making detailed statistics on the quantities completed in each bid section, and submits accurate progress plans to the company leaders and the municipal headquarters.
2. Solve and improve the engineering data. From now on, the technical department will concentrate on improving the data, ask the professionals in Wu Jian for guidance, and call the managers and librarians of each bid section to improve the data and review the rationality and authenticity of the data. Before Wednesday, the data of seven bids will be sorted out and reported to the company leaders.
3. General Manager X is responsible for solving the manhole cover problem as soon as possible. The quality should be guaranteed, the price should be reasonable and the blocks should be unified.
4. The technical department and the engineering department ensure that the guidance, service and supervision are in place. It is necessary to strengthen the on-site inspection of the project, and the inspection should be down-to-earth and not cursory. The key point is to supervise the construction of each bid section according to the drawing, and require the bid sections that are not constructed according to the drawing to be reworked and rectified; Report to the company leaders in time and take further measures for the blocks that have not been rectified. Strengthen the construction guidance of dangerous blocks, take protective measures for potential safety hazards in advance according to the design department's plan, and report to the headquarters in writing if it exceeds the design scope, and ask the headquarters to confirm. Ensure the safety of personnel, machinery and residents, and prevent the recurrence of similar accidents in the third standard.
5. The Engineering Department has strengthened coordination on the factors that affect the project construction: residents of three dangerous buildings in the third bid block obstruct the construction, the coal yard in the fourth bid block is to be demolished, materials are not allowed to enter and leave the hotel working face and Dongfanghong Avenue in the sixth bid block, and the river water level in the seventh bid block needs to be lowered, so it is necessary to coordinate the headquarters to solve it as soon as possible.
6. The Engineering Department is responsible for improving the emergency project of information three standards according to the requirements of the evaluation center.
7, the office is responsible for docking with headquarters to attend the regular meeting time and notify the relevant participants, each department according to the requirements of the office notice to attend the regular meeting.
8. With the technical department as the main body and the assistance of the office, according to the preliminary investigation data, various factors affecting the construction are listed and reported to the headquarters for coordination and processing in the form of documents, so as to strive for early summary, early reflection and early solution.
9. The technical department implements the change of design institute, and urges the first and second blocks to organize the construction according to the formal change opinions.
Third, Mr. Xu arranged the recent key work of the managers of each bid section.
Subsequently, Mr. Xu held a meeting of managers and department heads of each bid section. At the meeting, the progress of each bid was verified one by one, and the instructions of the municipal headquarters on the whole process of sewage pipeline in xx month were conveyed. Require each bid section to focus on the following work:
1, under the guidance of the technical department, arrange the librarians to complete the data arrangement within three days.
2. Each bid section has learned the lessons of the accident in Bid Section 3. For the construction of dangerous blocks and special blocks, protective measures should be taken in strict accordance with the design institute's plan. If no measures are taken, each bid section shall be responsible for compensating the losses.
3. Each bid section shall ensure "three guarantees": ensure the quality of the project, ensure the progress of the project, and ensure the safety of personnel, machinery and people along the way. It is necessary to strengthen construction, increase personnel and machinery, and increase the working face around the requirements of the municipal headquarters for connecting the new Shenhe sewage pipeline in xx month. Work countdown, the engineering department is responsible, the office assists, and reports the progress of the project every day to ensure that this work is in place.
4, in strict accordance with the requirements of the headquarters will be in and out of the material route, time, license plate number to the engineering department, summarized by the engineering department to the headquarters.
5. Pay attention to meteorological information at any time to ensure the safety of materials such as construction pipelines. If the materials are washed away by rain, all losses shall be borne by each bid section according to relevant regulations.
6. The riverbed buildings are hardened with rubble concrete according to the original scheme.
;